RITES - CRS Cheapest Alternative!

up
662 users have liked.

Cheapest Alternative

Sec 3.2  - Potential in terms of Capacity

Maximum Peak throughput:

Rail - 60000 Passengers/Hr

Metro - 40000 passenger/Hr

BRT - 500 Passengers/Hr

Sec 3.4 - Potential in terms of Cheapest Alternative

  • Metro costs 12000 Crores for 42.3 Km with carrying capacity of 1 Million (10 Lakhs) commuters per day.
  • CRS with 8000 Cr investment will yield 405 Km of CRS network and would carry about 2.5 Million commuters per day.
  • CRS could take the burden of 50% of greater Bangalore's total commuters population.

Sec 3.6 - Capacity Assesment Metro Vs CRS

  •  By its Width - Metro coach is 2.88 meters, CRS BG Coach is 3.66, i.e. it is 26% more.
  • By its length - Metro train - 6 Coaches, CRS train - 16 coaches, i.e. CRS train is 2.67 times of a metro train.

    Capacity of CRS train

                  1 CRS Train = 2.67 X 1.26 = 3.3 metro trains.

About a proposal to terminate CRS at City outskirts

Sec 4.5, Page 32, 2nd Para

"...Therefore, it is recommended not to terminate the commuter trains short of Bangalore. Terminals need to be the farthermost stations in the CRS i.e. Tumkur, Mandya, Bangarapet and Hosur etc. All other stations including major stations like Bangalore City, Yesvantpur etc. need to be passing through stations..."

Comments

Sanjeev's picture

With so much investment going on for Railway projects in B'lore

Following Railways works are taken up in Bangalore area with cost sharing in few cases between GoK & Railways :

1. There are 21 ROB / RUB's are at verious stages with SWR and BBMP.

Major two  ROB's are at Outer Ring Road  on MES road  on Tumkur line at Yesvanthpur station and next one is at Allalsandra on Bellary Road towards Yelahanka town.  All are cost sharing between BBMP & SWR on 50:50 basis.

2. Doubling of Yesvantpur - Yelahanka & Yelahanka - Channasandra Railway Track :  arround 50% physical work completed costing Rs 220 Crore.  Railways are spending

3. Electrification between Yesvantpur - Chikbanavar station ( 8 Kms )  Railways are spending.

4. Electrification between Yelahanka - Dodballapur (  part  of Gunthkal )

5. Yesvantpur Station upgradation on PF-1 side.

6. Nelamanagal Track  11 Kms is ready for opening.

7. Electrification between Kengeri - Mysore is in Progress on Cost Sharing basis between GoK & Railways.

Looking at these things and further few other works going on for additional foot over bridge at Bangalore city, Thrid entry at Bangalore city station, Integration of METRO at Baiyyappanahalli & Yesvantpur Station, Adarsh Station at Yelahanka, Dodballapur, Devanahalli.  

GoK  should realise  that it  has already invested in Railway infrastructure in Bangalore Division and should   send strong proposal for Commuter Rail case to Railway Board  taking RITES report as it is.

 

 

Sanjeev's picture

Notice to railways on suburban trains

A division bench headed by Chief Justice Vikramajit Sen ordered notice to the Railways and the state government with regard to a PIL seeking suburban rail services in Bangalore. Petitioner Satinderpal Chopra claimed that even though many cities like Mumbai, Kolkata, Ahmedabad and Hyderabad have been chosen for such a service, Bangalore has been neglected.

http://timesofindia.indiatimes.com/city/bangalore/HC-warns-BDA-against-piecemeal-approach-in-land-use-change/articleshow/14857106.cms

Praja.in comment guidelines

Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!