Transport Infrastructure Projects for Bengaluru Progressing nowhere

Infrastructure projects related to Projects mainly Commuter Rail, Light Rail, Monorail and BRTS is not progressing anywhere. Both the earlier BJP and Congress Governments have forgotten the CTTP reports and the recent survey done by a UK based company which already had prepared DPR for the light rail on the western half of Outer Ring Road and Magadi Road.

The Sorry state of affairs at KNDV Station

Commuter Rail

I visited the Krishna Deva Raya Station in Vijayanagar on Sunday. What is striking here is the absolute lack of infrastructure! Some issues with this station are:

(1) Lack of platforms

(2) A poorly deisgned box, which serves as the ticket counter

(3) The endless construction of the railway underpass

6.7 KM elevated road from Chalukya circle to Hebbal

Traffic jams

Hi

 

Today its officially declared that BDA is going ahead with Elevated Fly over from Chalukya Circle to Hebbal, My concern perhaps many have the same are as follows..

1. The flyover should not start from Sophia School. It should cross the signal at chalukya circle, otherwise they are encouraging traffic jams at chalukya circle

Decongesting roads to Whitefield - Moving cars or People?

Infrastructure

In past few weeks there have been lot of news on social media as well as in print /electronic media on attempts to provide that little relief to daily commuters travelling on Whitefield-CBD areas of Bengaluru City. There seems to be 2 distinct attempts and efforts for decongesting roads that leads to Whitefield from City Centers.

Suburban Rail / Urban Rail on PPP model : Indian Railway

Commuter Rail

With Cash starved ( suppose to be ) Indian Railway, looking at funding and operations of Suburban Rail under PPP :

Policies are getting fine tuned  for Urban Rail  Transport  during recent times :

Two more contentors for Namma Bengaluru award

Governance
Senior IAS officer M N Vijayakumar has asked the Chief Secretary to immediately remove Mir Anees Ahmed as special deputy commissioner, whom he has charged with corruption.

BMRC Ph-2 Tracking

Metro Rail

Majority of Construction contracts Tenders were suppose to be published during Q2/ Q3 and Q4  of 2013-14  and  balance works contract tenders to be called during  Q1/ Q2 / Q3 / Q4 of 2014-15

Alos Road widening and Road Streangthening ,  Demolution of properties Tenders were to be called during Q3/Q4  of 2013 -14

TenderSURE on Residency Road

TenderSURE is being discussed with some discontent these days because it has hit the road users community (dominated by motorvehicle users) hard. However its commendable that they continue with their work.

Prestige Shantiniketan Apartment Halt station near ITPL

Commuter Rail

Halt Railway station just 500 meters from ITPL will help thousands of IT folks to use Suburban Rail. Its high time Industry bodies,  IT companies and  Elected reps should come forward and get the halt station developed

 

Bangalore Coprehensive Traffic and Transportation Plan by KUIDFC fro RITES June'2011

Has the GOK /  IDD / DULT have the list of reports generated in the name of Bangalore Traffic and how much money have they spent on consultant ??? 

Syndicate content

Praja.in comment guidelines

Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!