Can someone tell when is the flyover construction at Agara junction to be completed ?
Vehicles must be allowed to take right from this junction at 27th Main. Also the one way implementation at 27th main HSR layout is not justified. AFter entering 27th main the road joining the agara village (1st cross) must be left open to public so that all vehicles need not go round about route. Few suggestions to improve traffic are -
- Allow right turn at 27th Main
- Allow LMV vehicles to go straight at agara/27main junction
- Extend 2 ways on 27th main till 1st cross
- Remove all the blockings made at 8/9/10/11 cross on 27th main and allow normal flow of traffic
- Re-route BMTC bus to paringipalya via Agara at earliest
Comments
Agara and Iblur Flyover progress
Both of these flyovers were supposed to be completed by 10-Apr-2010 as per the JNNURM boards at the construction sites. So there is already a one month delay. There is noticeable progress, and work is going on daily but there seems to be a lack of urgency.
Looks like the Iblur flyover will take a month and the Agara flyover another 3 months at least for completion. Since the madivala towards Iblur section of the Agara flyover is almost complete, I hope they push and complete this and let vehicles start plying on this. This will be an immediate relief for commuters on this route.