The Peripheral Ring Road is back. Not much new as far as the specs are concerned, but the big changes are, one, BDA (state govt) will be executing it, not NHAI (central govt) and two, it will be a PPP project.
[Pic: PRR Ph I as in 2005]
There were several reports across papers today (ET, Biz-standard) and here is a summary:
- 100 meters wide, 4 lanes each way, including 2 edge lanes dedicated for buses.
- 12 m wide center median for 'future' use (example cited - elevated mono rail)
- Tolled road. Though no clear documentation yet on the exits and interchanges
- Expect interchanges with all National highways for sure
- Phase 1 (60 km) will be taken up first. This would be the north east loop (Tumkur Road to Hosur Road cutting across via Old Madras Road, Malur).
- Claims of completing PRR Phase 1 in 30 months (TOI carried this, not Business-standard). Remember, the project concept is now 7-10 years old depending on whose claim you believe :)
- No mention yet of "intermodal" exchange (Metro to BRTS on PRR). But thats okay, I think PRR's primary purpose is to connect peripheral areas (ITPL to E-City for example) so that a lot of vehicles can just avoid the main city. Think of it as a modern version of "bye-pass" roads of old days.
Want to know more about PRR? Head to BDA website - Peripheral Ring Road
Sounds good, but I am interested in alignment of Phase II of PRR (the South loop). and its offset from NICE Peripheral road being done as part of BMIC. Two such high density roads so close to each other (and both tolled!) is perhaps not a good idea.
[Pic of phase II as in late 2005, source: BDA website back then]
ಪ್ರತಿಕ್ರಿಯೆಗಳು
Only half?
User Interaction Designer
Bangalore
Why not integrate with NICE on the West?
On the one hand we never seem to have funds for basic infrastructure - physical and social. On the other hand we want to duplicate roads. They need to extend NICE-PRR till NH7 rather than build another road.
PRR on the east side makes sense. At least they are starting with that stretch!
Does this mean that NICE-PRR is not going to see the light of day?
Srivathsa
Drive safe. It is not just the car maker which can recall its product.
Phase I - land already notified
I remember seeing long notifications about acquiring land along PRR Phase I back in March 2007 (last year!). So the work must be on I assume (along with usual controversies which will start surfacing now).
I think the fact that only Phase I has been given go ahead means that Phase II vs NICE Peripheral Road debate is alive. Making PRR Phase I PPP project? Well, is that like opening a door for NICE!? Government can't handpick NICE, but I am sure Kheney can't be stopped from making legal bids to be a partner here.
So bottomline, wait and watch, there should be more to come. But it better be done right, which means
No news yet on NICE
Was expecting some news on NICE before this..but anyways this will be good enough if BSY can get it completed in his tenure!
Its said this will be tolled so it sounds similar to NICE. As per the earlier plan the road was supposed to meet Hosur road near Attibele (Kr -Tn border)..so dont think it will cross BETL.
See this as providing connectivity to BIA...cos I guess it hits Belary road around yelahanka..
Hopefully we dont go wasting resources by doing the phII of the PRR and instead use NICE for it!
PRR after BG park - bad idea
User Interaction Designer
Bangalore
Toll collection
NICE and Kheny
blrsri,
Ashok Kheny of NICE is already a happy man and is planning some more projects
Ends with NICE - PRR
The 90% complete PRR needs to get finished..that was the only thing on my mind. I am not sure if the govt should be intersted in any of the other projects hes planning..
The Gowda family was up in arms against him causing lot of trouble for him and the project..they were wrong in certain ways but not in every way!
Highways, lets leave it to the NHAI..havent they done the Golden Quad? we can have other projects too executed by them..and have the level of transperancy that we need!
Instead of making real estate moghuls out of Road builders..we should be looking at fair and fast alternatives!
We all know the relaid mangalore highway is pretty good now and we are suggesting providing more trains..I think we should stop there and not let people build malls and huge resorts besides freeways on the fragile wester ghats ecosystem..Same applies to Karwar!
narayan
Eco friendly resorts
One could adopt eco friendly building methods in the Ghat region - see this for example: http://vernarch.com
Re: TS
User Interaction Designer
Bangalore
Laurie Baker
Cadambi
Now that you brought it up, I may add that a brother of mine, is supposed to be amongst the closest of Laurie Baker's disciples. His 'business' web-site is http://www.inspire-india....
Muralidhar Rao
PRR with BDA
PRR with BDA
welcome step if the following are taken care of
(1) PRR should be cemented
(2) there should not be any signals; sufficient underpasses or flyovers to be provided
(3) there should be a clearance of 100 feet from the edge of PRR to the nearest building(nice trees / flowers / grass can be planted in this space
Srinath Heragu
PRR tenders soon ante
Happy due to the cancellation of PRR2
To avoid the destruction of Bannerghata forest the PRR2 was directed towards Gottiger,Weavers Colony, Billawaradha halli, Shanubhogana Halli Kannayakana Agrahara and other adjoining areas.These areas are the main center for weavers. Hundreds of weavers suffered knowing that the PRR2 is directed towards their places which meant they would lose their jobs as many weaving centres were shifted to these areas due to Government orders and if PRR2 would be directed towards these areas then it would have caused a svere blow to thousands of weaving families .I am beyond happy that the construction of PRR2 has been cancelled. It was a restoration of peace to weavers and greenery to the Garden City.
M.S.Nagendra Founder-President Sri Sri Lakshmivenkateshwara Powerloom Co-op Society Ltd Weavers Colony, Gottigere,B.G.Road,Bangalore-83
mgstex@yahoo.com
Time to ask where this is?
Time to ask where this is? Anybody up for a meeting with BDA?
Meanwhile Hyderabad is provisioning for the future. Seen below is the access controlled 10 lane ORR being completed
BDA plans to start work on
BDA plans to start work on PRR
http://ibnlive.in.com/news/bda-plans-to-start-work-on-peripheral-ring-road/166122-60-119.html
CC: ibnlive
Ajay
Need latest map of PRR
Hi
Can someone post latest high resolution map of PRR?
Regards,
Varun