Bangalore City Station Developments
Submitted by Sanjeev on 28 June 2013 - 5:20pm
ಮೇಲೆ
241 users have liked.
Bangalore City: Proposed extension of Foot Over Bridge from Platform No 10 to MG colony.
Tender Cost : Rs 49,56,000/- within 3 month work to be completed after tender awarded
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1473&lang=0&id=0,3
With further Escalators, one more Foot Over Bridge which is still hanging and multilevel car parking, new entry from next to Kody Circle of DRM Office, these should make some difference to City Station and further 3.5 Acers of land with SWR, lets see how they will make difference to citizens
Groups:
- Login or register to post comments
- ಈ Project Blog ಅನ್ನು ಸ್ನೇಹಿತರಿಗೆ ಕಳಿಸಿ
ಬಳಕೆದಾರರ ಲಾಗಿನ್
Recent comments in this project
Similar Posts
- Memo to Minister of State for railways
- Tumkur MP demanding hourly train to Bangalore!
- Commuter Rail can make our city better
- Suburban Rail Progress - Railway Board & SWR Conversation
- South Western Railway - please wake up and listen to us!
- Kengeri to Whitefield Shuttle Train
- CM requesting Planning Commission to sanction Commuter Rail on cost sharing basis
ಪ್ರತಿಕ್ರಿಯೆಗಳು
Pit Lines getting extended at Bangalore city station
Bengaluru City -Modification to OHE due to extension of Pitlines at Mysore end
Tender Value : Rs 795572/-
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1650&lang=0&id=0,3
Provision of OHE top wiring on pitlines (1 to 4) and wiring of shunting neck at Bengaluru Cantonment end at Bengaluru City Railway station
Tender Value : Rs 671799/-
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1651&lang=0&id=0,3
Even though both tenders value is small, purose is very improtant and further SWR should invest in removing bottelnecks by investing MEMU Maintenance shed at Bayyappanhalli which will not cost more then Rs 10 Crore.
FOB Extension at City Station
1. Bangalore City: Proposed extension of Foot Over Bridge from Platform No 10 to MG colony.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1774&lang=0&id=0,3
Tender Value : Rs 6004745 /- but very good for commuters.
2. New Line : Hejjala - Halagur - Kanakpura :
Fixing of centre line and boundary stones and preparation of land plans and working plans for the new BG line between Hejjala and Halaguru via Kanakapura of Bangalore â?? Chamarajanagar section.(FLS-13/01)
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1754&lang=0&id=0,3
So south Bangalore on Kanakpur Road and arround Banashnkari VI phase BDA Layout people will get benefitted with Commuter Rail in future.
Bangalore city station Stabling line getting expanded
Construction of formation for stabling line / shunting neck at SBC Yard under ADEN/C/SBC jurisdiction.
Tender work cost : Rs 2.92 Crore, 4 months duration
http://www.swr.indianrailways.gov.in...9_SBC_1326.pdf
Finally Bangalore city getting some work tenders. So BYPL is getting ready for 3rd Terminal with 3/4 pit lines, stabling lines already exist.
So SBC getting expanded with Binny Mill land at SWR control of 3.5 Acers.
Renovation to flooring of PF 2/3 SW-II Repairs at Bangalore city
Bangalore City station : Renovation to flooring of PF 2/3 SW-II Repairs to running room
Tender work cost : Rs 1.04 Crore to be completed in 6 months.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=2167&lang=0&id=0,3
Status of City Station Pedestrian facility works progress
Status of Pedestrian facility at Bangalore City Station during last 5 years on 1. New Foot Over Bridge connecting all 10 Platforms on Cantonment end ( Chennai end ), 2. Extending existing FOB to Milk colony with wider FOB, 3. Extending subway from PF-1 to entrance of city station. Here is the status of all three works from SWR, after 4/5 years, SWR struggling to complet these simple works like BMRC struggling for MG road Station skywalk to connect plaza theater side since 3 years. Wake up SWR Bangalore, these are very much needed for passengers. How can SWR sleep on these during last 4 years where Railway Board has given clearance and funds too. No one to blame here except SWR officials only.
Already Bangalore is lacking proper pedestrain facility, even railways are also playing to BBMP / BDA actions.
At Rajajinagar Entrance on Bngalore City - Yesvantpur line
Construction of 8 lane corridor with loops, underpass and Road Under Bridge No.423 Km.0/500-600 between Bangalore City Junction and Yesvanthpur stations(ROB/SBC-YPR)
Tender work cost : Rs 23.71 Crore period of work : 12 months
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=2886&lang=0&id=0,3
Getting to the bus stand from
Getting to the bus stand from the railway station is an ordeal. The sub way is really bad. On so many occasions I have been forced to take the bus to Kengeri because of the stench of the sub way.
Expansion of City station has not been sent for Approval till no
SWR is have not yet firmed on the expansion of city station after shifting of Pit lines after PF10.
So even funds allocation is not their currently.
Still nong way to go to get expanded city station for better facility. Will Railway Minister look into this ???
Only METRO station at Milk Colony near Magadi road will be connected to City station existing FOB with walkalator
New Railway station building is planed for Okalipuram Birdge of 6 floors near Rajajinagar entrance, may be the above tender is for that looks like. I saw clearly station building location at PF 7-8 entrance close to Yesvanthpur line next to Church Here Railway has large chunck of land currenly holding.
2 more escalators at city station and 4 Nos at Yesvantpur
P { margin-bottom: 0.21cm; }A:link { }
1. BC- Civil works in connection with provision of lifts (02
nos) @ Bangalore city station
2. SBC - Civil works connected with provision of Escalator 2 Nos. at Bangalor e city station
P { margin-bottom: 0.21cm; }A:link { }
3. SW - I: YPR: Civil works connected with escalators on Platforms of 04 Nos.
4. SW - II YPR - Civil works in connection with provision of lifts (04 nos) @ Yeshavanthapur station
5. Construction of substructure of proposed new bridge in angalore city station back yard . (two tracks )
http://www.swr.indianrail...
6. YPR- Improvements to circulating area and widening of PF-1 by providing shelter, Flooring etc., duly dismantling existing old quarters and widening of approach road.
http://www.swr.indianrail...
Arround Rs 5.50 Crore worth tenders for Yesvantpur and Bangalore city station called.
Similar way Railway board takes up work at Baiyyappanhallai and Yelahnaka for making it terminal by allocating 10 crore per year, Bangalore can have full fledge 4 Terminals to handel intercity traffic
Bangalore City sttaion expansion
Traction OHE modification due to proposed Road under bridge at front yard of Bengaluru City Railway station
Tender Value : 5233028 /- Tender Called on n 15th Dec 2015
http://www.swr.indianrail...
SBC- Pro. Provision of third entry on STC side of platform No.1.
Tender Value : 13612577 Period of work : 6 Months Tender called on 14th Dec 2015
http://www.swr.indianrail...