SWR Tenders for Bangalore division - Will it help Namma Railu cause?
Submitted by Sanjeev on 5 January 2013 - 5:30pm
up
305 users have liked.
Here I am trying get all Tenders called by SWR in Bangalore Division. These infrastructure will help CRS implementation.
1. Yeshvanthpur: Extension of FOB from Platform 2/3 to 4, 5 & 6
Tender called on 28.05.2012 value : Rs 78.42 Lakhs, Duration of Completion 6 months from Tender award.
Till now no progress on the ground and this is not getting connected to METRO station which will be drawback.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=100&lang=0&id=0,3
Groups:
- Login or register to post comments
- Forward this Project Blog
User login
Recent comments in this project
Similar Posts
- NammaRailu 2010 Roundtable - Press Release
- Commuter Rail meeting with Chief Secretary, GoK
- Commuter Rail starting service soon
- Common mobility card
- Malur needs Commuter Rail badly
- Proceedings of DULT meeting on 2012 RITES Report on Bengaluru CRS !
- Binny Mill Land (Next to City Railway Station) - Who owns it ?
Comments
ROB at Hoody costing Rs 7.86 Crore
Construction of approaches on both sides of Road Over Bridge in lieu of LC.No.133 at Railway Km.337/400-500 between Krishnarajapuram - Whitefield Railway station near Hoodi.( ROB/LC133AP)
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=27&lang=0&id=0,3
Tender was called in June'2012, any progress on the ground and how this will help vechile movement and also Train movements, any one has throw the light on this
ROB at Sarjapur Road : between Heelalige & Carmelram station
Construction of Road Over Bridge in lieu of LC No.131 at Km.192/600-700 (Sarjapur Road) between Heelalige and Carmalram Railway station.(ROB/LC-131)
Cost Rs 17.27 Crore
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=124&lang=0&id=0,3
Tender was called in July'2012 , any progress as time rovided is 12 Months.
Yesvantpur Station getting small improvements
Yeshwanthpur - Pro construction of station building on PF-1 side
Cost of Tender Rs 62.36 Lakhs, Tender called, on 01.06.2012, 6 months for completion
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=152&lang=0&id=0,3
SW-I: Yeshvanthpur - Pro Provision of IRS type platform shelter for 5 bays on PF No.6 on TK end. SW-II:YPR-Provision of IRS type platform shelter for 10 bays on PF No.1 on SBC and TK ends.
Tender work Cost : 1.16 Crore, Tender dt : 26.09.2012, period for completion 6 months
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=591&lang=0&id=0,3
These small things including FOB extending to 4,5 & 6 PF should help id disburing passengers fast.
ROB at Jakkur for Doubling line
Proposed Construction of Road Over Bridge of span 1x30.5m (Composite girder) + 6 x 30.50m (PSC) with sub-way RCC box 1x3.50m x2.5m by Box Pushing Technique in lieu of LC.No.11 at Km.13/300-400 between Channasandra and Yelahanka station on SBC-DMM section near Jakkur. (YNK-ROB/LC11)
Tender Wok : Rs 12.19 Crore was called in July'2012, 18 months for completion
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=174&lang=0&id=0,3
I have not seen any ground work at this gate till now.
Pit Lines at Baiyyappanhalli 2 No's & one stabling line
Bangalore City Jolarpettai section: Provision of 2 Pit Lines & One stabling Line for a length of 580 Mtrs at BYPL marshalling yard (BYPL 3rd coaching terminal Phase I)
Value Rs 8,12,68,681
Baiyyappanahalli: Civil works in connection with 3rd coaching terminal Phase I in ADEN/C/SBC jurisdiction.
Value Rs2,21,70,961
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=39&lang=0&id=0,3
Baiyyappanahalli - Proposed new pitline 580mtrs of 2Nos - Electrical arrangements
Value Rs 38.68 Lakhs
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=191&lang=0&id=0,3
so finally Baiyyappanhalli is getting developed, good sign for CRS
Signal and Telecommunication for Interlocking of Level Crossin
Provision of signaling arrangements in connection with Interlocking of 11 LC Gates over Bangalore division. (LC No.15, 18, 22, 25 & 28 in BYPL-DMM, LC No. 9 & 10A (YPR-YNK), 22 & 24 (YNK-CBP), 35 (SBC-TK), LC.No.91 between JTJ-SKPT section over Bangalore division.)
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=179&lang=0&id=0,3
Whats effect on Train Running on these section as work is costing Rs 1.64 Crore
One more FOB at Bangalore city station
Bangalore City: Provision of FOB 135m long between Platform No.1 to 10, MAS end.
Costing Rs : 2.32 Crore and Tender was called in Aug'2012. 24 month for completion.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=228&lang=0&id=0,3
Doddaballapur: Proposed FOB from PF No 1 to 2 in connection with
1. Doddaballapur: Proposed FOB from PF No 1 to 2 in connection with Adarsh station.
Tender Cost Rs 79.20 Lakhs and 6 months for completion.
Tender was called in June'2012.
2. Bangalore Cantonment: CC Apron for Road No 1 for a length of 580 Mtrs
Tender work cost Rs 98 Lakhs and 30 days completion, that means this work should comleted, whats effect on the Track avalibity ??
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=237&lang=0&id=0,3
Bangalore City-Dharmavaram: Provision of PF shelter IRS type 6 Bays on PF-4 @ HUP, 6 Bays on PF-1 @ GBD & 6 Bays @ Island PF 2/3 @ DBU.
Dodballapur station getting Plaforms shelters for PF 2 & 3
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=869&lang=0&id=0,3
Intermediate Blocak Section between Cant & Baiyyappanahalli
Provision of IBS at Km.348.885 between BNC-BYPL in SBC-JTJ section.
Tender work cost Rs : 56.51 Lakhs and was called on 4th July'2012, 4 months for completion.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=241&lang=0&id=0,3
this was one of the short coming pointed out by RITES report in reducing block size between SBC - Bangarpet
This work should be completed by now
RUB between Nayandahalli - Kengeri at Dubbasipalya
Construction of Road Under Bridge in lieu of LC No.10 at KM.11/100-200 (Dubbasipalya) including approaches between Nayandahally and Kengeri Railway stations in Bangalore city - Mysore section. (NYH-RUB/LC10)
Tender work cost : Rs 9.04 Crore
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=239&lang=0&id=0,3
Banswadi station getting upgraded with Intercity Trains stoppin
Banaswadi: SW-I Improvements to station building, circulating area, PF and approach road and parking facilities. SW-II Construction of boundary wall between LOGH-BAND for a length of 650 Mtrs
Tender work cost : Rs 67.98 Lakhs and period of completion 6 months, tender called in July'2012
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=309&lang=0&id=0,3
With Railway reservation counter opening and couple of Intercity trains stopping, this station is really coming up.
At Devanhalli station Track work
Devanahalli: Through ballast recoupment for a length of 45.90 Kms between Km 0.0 to 45/900 by collection and supply of machine crushed ballast @ Devanahalli Depot including mechanical loading, boxing, unloading in SE/P Way/YNK section.
Tender work costing Rs : 2.43 Crore
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=391&lang=0&id=0,3
RUB at Kengeri station Yard
Bangalore city-Mysore : Proposed 1 x 9.50m x 3m RCC Box @ Km 12/700-800 @ Kengeri station Yard by (pushing 15 m long + cast in situ 12m long).
Tender Work : Rs 1.90 Crore.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=437&lang=0&id=0,3
Bansawadi, Baiyyappanahalli, Carmelram Sations getting improveme
SW-I Banaswadi: Provision of IRS type PF shelter on PF-1 10 Bays. SW-II Raising & extension of PF @ Carmeloram station
Tender work cost : Rs 1.12 Crore,
Baiyyappanahalli: Provision of IRS type PF shelter @ PF 1 10 Bays
Tender work Cost : Rs 74 Lakhs
http://www.swr.indianrailways.gov.in/swr/notice/1357190762368_BACiv39_SBC_1297.pdf
Tender called on 26.12.2012, six month period for compleion. Tender to be opened in Feb'2013
Banswadi & Baiyyappanhalli station are getting infrastructure upgradation.
RUB at Yesvanthpur Bypass line toYesvanpur Pit Line
Construction of RUB near LC No. 4 & 4B at km 7/600-700 on Yeshwantpur - Tumkur line & Yeshwantpur Bypass on Outer ring road near Jalahalli for the entry to sleeper factory, coach stabling & pit line near Yeshwantpur yard (YPR-TK/92)
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=955&lang=0&id=0,3
Tender work cost : Rs 2.13 Crore tender called 22.12.2012
Two more RUB's between Bangalore - Tumkur & Chikballapur
Bangalore City - Tumkur section: Construction of RUB in lieu of 2 Level Crossings
Tender work costing : Rs 2.36 Crore, 6 months for completion
Yelahanka - Chickaballapur: Proposed construction of RUB's in lieu of Level Crossings by cut and cover method.
Tender work costing : Rs.3.07 Crore, 5 Months for completion
Tender was called on 11.12.2012, Tender to be opened in Jan'2012
http://www.swr.indianrailways.gov.in/swr/notice/1355552855239_BACiv38_SBC_1296.pdf
SWR is not running other then 2 Trains to Chikballpur & they say running passenger Trains on this segment ie YPR - Devanhalli is no patronaged, why are they invesing so much on Chikballpur segment.
I think we should get the details thru RTI : how much SWR is spending amount on mainting Tracks & Stations on Yelahanka - Chikballapur & Chikbanavar - Nelamangala during last 2/3 years.
Chikbanavar FOB extending oustside the PF.
Chickabanawara: Proposed FOB from existing FOB on PF No 4/5 to outside crossing the PQRS tracks.
Tender work costing Rs 47 Lakhs , Tender called on 11.12.2012, period of completion 4 months.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=871&lang=0&id=0,3
SWR should replicate this station development at Yelahanka, Dodballapur, Baiyyappanhalli
City Station PF shelter getting upgraded
Bangalore City: Proposed replacement of AC sheet with galvanized trapezoidal MS sheet on PF 1 (2700 Sqm), 2&3 (1800 Sqm), 4 (2800 Sqm), 5&6 (2000 Sqm) 9&10 (1900 Sq)
Tender work Cost : Rs 96 Lakhs, Tender called in Nov'2012
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=759&lang=0&id=0,3
Rajankunte Station second loop
Rajankunte: Provision of signaled second loop with CSLof 715 Mtrs
Tender cost : Rs 1.05 Crore, Tender called on 14th Nov'2012
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=761&lang=0&id=0,3
Raising & extension of PF @ Rajankunte by 420 Mtrs & Gowribidanur by 540 Mtrs
Tender work cost : 77.62 Lakhs, Tender was called in Oct'2012
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=473&lang=0&id=0,3
Whitefield line some tenders
Bangalore City-Jolarpettai: SGT ( Satelite Goods Terminal ) Proposed extension of pit line for a length of 300 Mtrs
Tender work Cost :Rs 1.35 Crore, Tender called on 14.11.2012
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=762&lang=0&id=0,3
These pit lines should help in goods Train receipt & despaches very fast arround Bangalore
Whitefield - Kolar as part of Commuter Rail after line completi
Looking at the tenders called by SWR on Whitefield - Kolar for 50 Kms, their may be demand after 3 years. Following Tenders called last month of high value 4 Tenders worth 94 Crore called for new Track between Kolar - Whitefield.
1. Whitefiled â?? Kolar new BG line-Earthwork in embankment & cutting, minor bridges, side drains in cuttings masonry walls in platform from Km. Km.40000 to 484000 (including Cheluvanahalli halt stations between Narasapura and Kolar stations. (TWO PACKET SYSTEM)(WFD-KQZ/03)
Tender value : Rs 28.78 Crore
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=952&lang=0&id=0,3
2. Whitefiled â?? Kolar new BG line â?? Construction of ROB/RUB, including approach road works and other miscellaneous works from Km.40000 to 48400 between Narasapura and Kolar stations.(TWO PACKET SYSTEM)(WFD-KQZ/05)
Tender value : Rs 19.22 Crore
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=954&lang=0&id=0,3
3. Whitefiled â?? Kolar new BG line - Earthwork in embankment & cutting, minor bridges, side drains in cuttings masonry walls in platform from Km.32000 to 40000 (including Narasapura crossing station) between Narasapura and Kolar station (TWO PACKET SYSTEM) (WFD-KQZ/02)
Tender Value : Rs 23.86 Crore
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=951&lang=0&id=0,3
4. Whitefiled â?? Kolar new BG line â?? Construction of RUB, including approach road works and other miscellaneous works from Km.32000 to 40000 (including Narasapura Crossing station) between Narasapura and Kolar section . (TWO PACKET SYSTEM) (WFD-KQZ/04)
Tender Value : Rs 21.49 Crore
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=953&lang=0&id=0,3
All these tenders are having 11 / 12 months compleion time.
Also my 2nd thought on how did GOK & SWR manage to acquire so much of land in such short time between Whitefield - Kolar
Krishanrajapurma Station getting upgraded
Krishnarajapuram: Provision of PF shelter IRS type on PF 4 for 20 Bays.
Tender work Cost :1.53 Crore, 12 Months completion, Tender called on 12.10.2012
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=712&lang=0&id=0,3
Krishnarajapuram: Pro construction of new station building with provision of booking office, concourse, waiting hall, toilet facilities, circulating area etc.,
Tender work Cost : 1.29 Crore, 12 Months completion, Tender called on 12.10.2012
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=716&lang=0&id=0,3
Yelahanka station getting face lift
Yelahanka: Construction of new station building, Provision of PF, PF shelters, circulating area, Pay & Use toilets in connection with Adarsha Station.
Tender work cost : 1.57 Crore, Tender called 26.09.2012, 8 month for completion
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=596&lang=0&id=0,3
This is part of Adarsh station like Dodballapur, Devanhalli, Chikballapur, Yelahanka
ROB for Yelahanka new town at Allalsandra
Construction of Road Over Bridge including approaches in lieu of LC.No.11 at Km.15/700-800 near Allalasandra in Yeshwanthpur - Yelahanka section. (YNK-ROB/03)
Tender work cost : 19.84 Crore, called in sept'2012, 18 month completion.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=564&lang=0&id=0,3
Construction of limited height sub-way (RUB) including approaches at Km.14/800-900 near Judicial layout in Yeshwanthpur - Yelahanka section.(YNK-RUB/04)
Tender work cost : Rs 4.93 Crore, called in sept'2012, 12 months for completion.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=565&lang=0&id=0,3
ROB for Yelahanka new town at Allalsandra
Construction of Road Over Bridge including approaches in lieu of LC.No.11 at Km.15/700-800 near Allalasandra in Yeshwanthpur - Yelahanka section. (YNK-ROB/03)
Tender work cost : 19.84 Crore, called in sept'2012, 18 month completion.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=564&lang=0&id=0,3
Construction of limited height sub-way (RUB) including approaches at Km.14/800-900 near Judicial layout in Yeshwanthpur - Yelahanka section.(YNK-RUB/04)
Tender work cost : Rs 4.93 Crore, called in sept'2012, 12 months for completion.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=565&lang=0&id=0,3
4 more Subway to elimanate LC's on Tumkur segment
Baiyyappanahalli - Tumkur: Proposed subway in lieu of LCs (4 Nos) RCC Box by rolling in / launching method (Single track)
Tender work cost : Rs 4 Crore, Tender called in Oct'2012, 8 months completion
http://www.swr.indianrailways.gov.in/swr/notice/1349862670943_BACiv34_SBC_1292.pdf
Kyatasandra goods yard : Beeing moved from Tumkur station
Kyatasandra - Proposed goods yard arrangements by regrading of Up & down main line along with other ancillary works from Km.62 to Km.64 and Tumkur -regrading for existing line from Ch.69/800 to 72/500 and temporary diversion from Ch.71/000 to 72/100, extension of bridges retaining wall and other miscellaneous works in YPR-TK section (Additional works).(YPR-TK/91)
Tender work cost : 7 Crore, called in sept'2012, 8 months for completion.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=566&lang=0&id=0,3
Escalators for Yesvantpur station and Bangalore city
4 Escalaors for Yesvantpur & 2 Escalaors for Bangalore city sancion and tenders called in Dec'2012
This info is their on Indian Railway website
ROB at ORR from MES road towards NH-4 Tumkur Road
This ROB tender work costing Rs 20 Crore was called in Jan'2012 and physical work has been started and looks like this may be completed in 2 years looking at phyisical progress.
http://www.swr.indianrailways.gov.in/swr/notice/1325663641374_Item%2003%20OT-001-12.pdf
This will allow seamless train movement on Yesvantpur - Chikbanavar
Nayandahalli Station Should had some improvements
There should be some plan to improve Nayandahalli station for easier interchange to ORR bus stop and Namma Metro Station. Also for the proposed Light Rail.
Train fares to go up from January 21
The comments has been reloacted Here as a full discussion post - Admin
Note: Lets keep this post for tracking the railway works around Bengaluru, coinciding with the Namma Railu proposals. For any other railway issues, pls feel free to open new discussion threads.
Yeshwantpur Railway Station
I am happy to see this segment.
There is enough land next to Yeshwantpur railway station, towards Lottegollahalli, which as I have noticed, is vacant. Can somebody tell me whether this is owned by the railways or someone else? If at all it is owned by the railways, then would it not be a good idea to plan the expansion of Yeshwantpur station, or build a brand new terminus there, allowing the existing station to be a stop over station for commuter rail and the long distance trains on the Bangalore - Tumkur and Bangalore - Hassan (in future) segments??
This however, does not mean that the work on a third terminus at Byappanahalli must be stopped. Bangalore has grown so intensely that it requires multiple terminals; the scope for expanding the existing ones must be explored along with constructing new ones...
Tejaswi
Other routes within Bangalore for commuter rail
Guys, I am as much an enthusiast of commuter rail in Bangalore as many of you here. Hence I intend to share a few thoughts of mine on commuter rail in this segment, which I feel has been specifically dedicated to it.
Doddaballapur - Devanahalli - Whitefield new railway line is desirable as Doddaballapur is now turning out to be the new happening residential locality of Bangalore. ITIR and Hardware park once operational would increase the number of people to and from Devanahalli, while one hardly needs to say anything about Whitefield. Hence a commuter rail network along this route would be most needed in future.
Yelahanka / Rajanukunte - Nelamangala railway line is also desirable as there have been talks of converting it into a terminus in the RITES report. Once this line is laid, besides serving commuter rail, it would also help the long distance trains from Hubli, Shimoga, Mangalore, Hassan etc. to be terminated at Yelahanka.
Bidadi - Harohalli - Bannerghatta - Anekal town - Attibele - Sarjapur - Varthur - Whitefield new railway line would enable commuter rail, as also enable trains from Mysore towards Chennai, Salem, Tirupati etc. to avoid the ever-busy Bangalore city station, thereby creating more space for suburban trains besides enabling more long distance trains to be started from the city station.
Tejaswi
@Tejeswi, New Railway Lines!
Tejaswi,
The new railway lines that you mentioned in your comments are needed in long term if not today. If you read RITES 2012 report, you will find the recommendation for building a circular rail network around the periphery of Bangalore. The routes more or less connect these places
We have a big problem on our hand. GOK, state politicians have not put together a list of railway infrastructure that is needed in Bangalore and other parts of the state. In fact if you go through the Loksabha Questions, you would hardly find any demands from new line, additional infrastructure. It seems they are least interested in getting railway projects for state. Come Feb/March, they are ready for making noises as they do every year saying railways in discriminating the state. In last 5 years, only about 25 questions have been asked by state MPs to the Railway Ministry. In that City MPs draws blank. One can imagine why railways is absent in our state.
It is time we knock on our political representatives and hand them a wish list. We alone are to be blamed for state of railways in our state. Can't expect others to do our work.
In a nutshell, we the people of this state, our MPs/MLAs, our government has not demanded enough railway projects that we need. Therefore the blame squarely lie with us.
Some more tenders on Yelahanaka - Channasandra doubling & ROB
Proposed construction of Road Under Bridge in lieu of LC No.6 Km.5/800-900 size 1 x 8.25 x 4.50 RCC box and RUB in lieu of LC.No.8 at Km.10/400-500 RCC box 1x8.25x4.5 between Channasandra - Yelahanka section. (TWO PACKET SYSTEM) (YNK- CSDR/17)
Value Rs : 108876261 Date : 22-01-2013
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1052&lang=0&id=0,3
Yelahanka - Channasandra doubling project - Construction of S&T accommodation, platforms, shelter, FOB, yard drainage with passenger amenities at Yelahanka and Channasandra stations. (YNK-CSDR/19 )
Value Rs : 36480960 Date : 22-01-2013
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1054&lang=0&id=0,3
Proposed construction of Road under Bridge 1 x 10.5 x 4.50 (Bridge proper in Railway limits only) RCC box in lieu of LC No.9, at Km.11/300-400M and Proposed construction of Road Under Bridge 1 x 9.50 x 4.00 RCC box near by LC No.10 at Km.12/500-600 between Yelahanka â?? Channasandra section.(YNK-CSDR/18)
Value Rs : 88116131 Date : 22-01-2013
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1053&lang=0&id=0,3
Yelahanka - Channasandra doubling project - Construction of S&T accommodation, platforms, shelter, FOB, yard drainage with passenger amenities at Yelahanka and Channasandra stations. (YNK-CSDR/19 )
Value Rs : 36480960 Date : 22-01-2013
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1054&lang=0&id=0,3
Station Lighting and Electronic Interlocking System @ Tumkur
Electrical arrangements in the platform shelters and raised /extended platforms at various stations in Bangalore Division
Value : Rs 30 Lakhs
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1027&lang=0&id=0,3
Design, supply, installation testing and commissioning of Electronic Interlocking System (EI System) at Tumkur station of Bangalore division in connection with New Line between TK-RDG Section.
Value Rs : 1.35 Crore Date : 19-01-2013
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1031&lang=0&id=0,3
So Tumkur is getting developed as good junction and SWR should take up electrification on this Tumkur - Chikbanavar soon
Kengeri Station getting PF shelters
Kengeri Station :
Kengeri: Provision of PF shelter on PF 2 & 3 IRS Type 6 Bays SW-II Provision of PRS building at First Floor & Extn of two wheeler parking.
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1125&lang=0&id=0,3
Tender Work Value : Rs 62.2 Lakhs
Banswadi Station :
Provision of Second Loop with CSL of 715 mtrs. with high level platform of 540 mtrs at BAND station in YPR-SA section of Bangalore Division
http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1164&lang=0&id=0,3
Tender Work Value : Rs 36.51 Lakhs