SWR Tenders for Bangalore division - Will it help Namma Railu cause?

up
305 users have liked.
Commuter Rail

Here I am trying get all Tenders called by SWR in Bangalore Division. These infrastructure will  help CRS implementation.

 

1. Yeshvanthpur: Extension of FOB from Platform 2/3 to 4, 5 & 6

Tender called on 28.05.2012  value : Rs 78.42 Lakhs,  Duration of Completion 6 months from Tender award.

Till now no progress on the ground  and this is not getting connected to METRO station which will be drawback.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=100&lang=0&id=0,3

 

 

Groups:

Comments

ROB at Hoody costing Rs 7.86 Crore

up
171 users have liked.

Construction of approaches on both sides of Road Over Bridge in lieu of LC.No.133 at Railway Km.337/400-500 between Krishnarajapuram - Whitefield Railway station near Hoodi.( ROB/LC133AP)

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=27&lang=0&id=0,3

Tender was called in June'2012,  any progress on the ground  and how this will help vechile movement and also Train movements, any one has throw the light on this

ROB at Sarjapur Road : between Heelalige & Carmelram station

up
172 users have liked.

Construction of Road Over Bridge in lieu of LC No.131 at Km.192/600-700 (Sarjapur Road) between Heelalige and Carmalram Railway station.(ROB/LC-131)

Cost Rs 17.27 Crore

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=124&lang=0&id=0,3

Tender was called in July'2012 ,  any progress  as time rovided is 12 Months.

Yesvantpur Station getting small improvements

up
195 users have liked.

Yeshwanthpur - Pro construction of station building on PF-1 side

Cost of Tender Rs 62.36 Lakhs, Tender called,   on 01.06.2012, 6 months for completion

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=152&lang=0&id=0,3

SW-I: Yeshvanthpur - Pro Provision of IRS type platform shelter for 5 bays on PF No.6 on TK end. SW-II:YPR-Provision of IRS type platform shelter for 10 bays on PF No.1 on SBC and TK ends.

Tender work Cost : 1.16 Crore, Tender dt : 26.09.2012, period for completion 6 months

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=591&lang=0&id=0,3

These small things including FOB extending to 4,5 & 6 PF should help id disburing passengers fast.

ROB at Jakkur for Doubling line

up
165 users have liked.

Proposed Construction of Road Over Bridge of span 1x30.5m (Composite girder) + 6 x 30.50m (PSC) with sub-way RCC box 1x3.50m x2.5m by Box Pushing Technique in lieu of LC.No.11 at Km.13/300-400 between Channasandra and Yelahanka station on SBC-DMM section near Jakkur. (YNK-ROB/LC11)

Tender Wok : Rs 12.19 Crore was called in July'2012,  18 months for completion

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=174&lang=0&id=0,3

I have not seen any ground work at this gate till now.

Pit Lines at Baiyyappanhalli 2 No's & one stabling line

up
165 users have liked.

Bangalore City Jolarpettai section: Provision of 2 Pit Lines & One stabling Line for a length of 580 Mtrs at BYPL marshalling yard (BYPL 3rd coaching terminal Phase I)

Value Rs 8,12,68,681

Baiyyappanahalli: Civil works in connection with 3rd coaching terminal Phase I in ADEN/C/SBC jurisdiction.

Value Rs2,21,70,961

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=39&lang=0&id=0,3

Baiyyappanahalli - Proposed new pitline 580mtrs of 2Nos - Electrical arrangements

Value Rs 38.68 Lakhs

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=191&lang=0&id=0,3

so finally Baiyyappanhalli is getting developed,  good sign for CRS
 

Signal and Telecommunication for Interlocking of Level Crossin

up
180 users have liked.

Provision of signaling arrangements in connection with Interlocking of 11 LC Gates over Bangalore division. (LC No.15, 18, 22, 25 & 28 in BYPL-DMM, LC No. 9 & 10A (YPR-YNK), 22 & 24 (YNK-CBP), 35 (SBC-TK), LC.No.91 between JTJ-SKPT section over Bangalore division.)

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=179&lang=0&id=0,3

Whats effect on Train Running on these section as work is costing Rs 1.64 Crore

 

One more FOB at Bangalore city station

up
178 users have liked.

Bangalore City: Provision of FOB 135m long between Platform No.1 to 10, MAS end.

Costing Rs : 2.32 Crore and Tender was called in Aug'2012.  24 month for completion.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=228&lang=0&id=0,3

Doddaballapur: Proposed FOB from PF No 1 to 2 in connection with

up
171 users have liked.

1. Doddaballapur: Proposed FOB from PF No 1 to 2 in connection with Adarsh station.

Tender Cost Rs 79.20 Lakhs and 6 months for completion.

Tender was called in June'2012.

2. Bangalore Cantonment: CC Apron for Road No 1 for a length of 580 Mtrs

Tender work cost Rs 98 Lakhs  and  30 days completion,  that means this work should comleted,  whats effect on the Track avalibity ??

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=237&lang=0&id=0,3

Bangalore City-Dharmavaram: Provision of PF shelter IRS type 6 Bays on PF-4 @ HUP, 6 Bays on PF-1 @ GBD & 6 Bays @ Island PF 2/3 @ DBU.

Dodballapur station getting Plaforms shelters for PF 2 & 3

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=869&lang=0&id=0,3

 

Intermediate Blocak Section between Cant & Baiyyappanahalli

up
154 users have liked.

Provision of IBS at Km.348.885 between BNC-BYPL in SBC-JTJ section.

Tender work cost Rs : 56.51 Lakhs  and was called  on 4th July'2012,   4 months for completion.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=241&lang=0&id=0,3

this was one of the short coming pointed out by RITES report in reducing block size between SBC -  Bangarpet

This work should be completed by now 

RUB between Nayandahalli - Kengeri at Dubbasipalya

up
193 users have liked.

Construction of Road Under Bridge in lieu of LC No.10 at KM.11/100-200 (Dubbasipalya) including approaches between Nayandahally and Kengeri Railway stations in Bangalore city - Mysore section. (NYH-RUB/LC10)

Tender work cost : Rs 9.04 Crore

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=239&lang=0&id=0,3

Banswadi station getting upgraded with Intercity Trains stoppin

up
168 users have liked.

Banaswadi: SW-I Improvements to station building, circulating area, PF and approach road and parking facilities. SW-II Construction of boundary wall between LOGH-BAND for a length of 650 Mtrs

Tender work cost : Rs 67.98 Lakhs and period of completion 6 months, tender called in July'2012

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=309&lang=0&id=0,3

With Railway reservation counter opening and couple of Intercity trains stopping,  this station is really coming up.

At Devanhalli station Track work

up
167 users have liked.

Devanahalli: Through ballast recoupment for a length of 45.90 Kms between Km 0.0 to 45/900 by collection and supply of machine crushed ballast @ Devanahalli Depot including mechanical loading, boxing, unloading in SE/P Way/YNK section.

Tender work costing Rs : 2.43 Crore

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=391&lang=0&id=0,3

RUB at Kengeri station Yard

up
171 users have liked.

Bangalore city-Mysore : Proposed 1 x 9.50m x 3m RCC Box @ Km 12/700-800 @ Kengeri station Yard by (pushing 15 m long + cast in situ 12m long).

Tender Work : Rs 1.90 Crore.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=437&lang=0&id=0,3

Bansawadi, Baiyyappanahalli, Carmelram Sations getting improveme

up
159 users have liked.

SW-I Banaswadi: Provision of IRS type PF shelter on PF-1 10 Bays. SW-II Raising & extension of PF @ Carmeloram station

Tender work cost : Rs 1.12 Crore, 

Baiyyappanahalli: Provision of IRS type PF shelter @ PF 1 10 Bays

Tender work Cost : Rs 74 Lakhs

http://www.swr.indianrailways.gov.in/swr/notice/1357190762368_BACiv39_SBC_1297.pdf

Tender called on 26.12.2012,  six month period for compleion.  Tender to be opened in Feb'2013

Banswadi & Baiyyappanhalli station are getting infrastructure upgradation.

RUB at Yesvanthpur Bypass line toYesvanpur Pit Line

up
166 users have liked.

Construction of RUB near LC No. 4 & 4B at km 7/600-700 on Yeshwantpur - Tumkur line & Yeshwantpur Bypass on Outer ring road near Jalahalli for the entry to sleeper factory, coach stabling & pit line near Yeshwantpur yard (YPR-TK/92)

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=955&lang=0&id=0,3

Tender work cost : Rs 2.13 Crore  tender called 22.12.2012

Two more RUB's between Bangalore - Tumkur & Chikballapur

up
164 users have liked.

Bangalore City - Tumkur section: Construction of RUB in lieu of 2 Level Crossings

Tender work costing : Rs 2.36 Crore,  6 months for completion

Yelahanka - Chickaballapur: Proposed construction of RUB's in lieu of Level Crossings by cut and cover method.

Tender work costing : Rs.3.07 Crore,  5 Months for completion

Tender was called on 11.12.2012,  Tender  to be opened  in Jan'2012

http://www.swr.indianrailways.gov.in/swr/notice/1355552855239_BACiv38_SBC_1296.pdf

 

SWR is not running other then 2 Trains to Chikballpur & they say running passenger Trains on this segment ie YPR - Devanhalli is no patronaged,  why are they invesing so much on Chikballpur segment. 

I think we should get the details thru RTI : how much SWR is spending amount on mainting Tracks & Stations on Yelahanka - Chikballapur & Chikbanavar - Nelamangala during last 2/3  years.

 

Chikbanavar FOB extending oustside the PF.

up
170 users have liked.

Chickabanawara: Proposed FOB from existing FOB on PF No 4/5 to outside crossing the PQRS tracks.

Tender work costing Rs 47 Lakhs ,  Tender called on 11.12.2012,  period of completion 4 months.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=871&lang=0&id=0,3

SWR should replicate this station development at Yelahanka, Dodballapur, Baiyyappanhalli

City Station PF shelter getting upgraded

up
172 users have liked.

Bangalore City: Proposed replacement of AC sheet with galvanized trapezoidal MS sheet on PF 1 (2700 Sqm), 2&3 (1800 Sqm), 4 (2800 Sqm), 5&6 (2000 Sqm) 9&10 (1900 Sq)

Tender work Cost : Rs 96 Lakhs,  Tender called in Nov'2012

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=759&lang=0&id=0,3

Rajankunte Station second loop

up
179 users have liked.

Rajankunte: Provision of signaled second loop with CSLof 715 Mtrs

Tender cost : Rs 1.05 Crore,  Tender called on 14th Nov'2012

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=761&lang=0&id=0,3

Raising & extension of PF @ Rajankunte by 420 Mtrs & Gowribidanur by 540 Mtrs

Tender work cost : 77.62 Lakhs, Tender was called in Oct'2012

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=473&lang=0&id=0,3

 

 

Whitefield line some tenders

up
187 users have liked.

Bangalore City-Jolarpettai: SGT ( Satelite Goods Terminal ) Proposed extension of pit line for a length of 300 Mtrs

Tender work Cost :Rs 1.35 Crore, Tender called on 14.11.2012

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=762&lang=0&id=0,3

These pit lines should help in goods  Train receipt & despaches very fast arround Bangalore

 

 

 

Whitefield - Kolar as part of Commuter Rail after line completi

up
171 users have liked.

Looking at the tenders called by SWR on Whitefield - Kolar for 50 Kms,  their may be demand after 3 years.  Following Tenders called last month of high value 4 Tenders worth 94 Crore called for new Track between Kolar - Whitefield.

1. Whitefiled â?? Kolar new BG line-Earthwork in embankment & cutting, minor bridges, side drains in cuttings masonry walls in platform from Km. Km.40000 to 484000 (including Cheluvanahalli halt stations between Narasapura and Kolar stations. (TWO PACKET SYSTEM)(WFD-KQZ/03)

Tender value : Rs 28.78 Crore

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=952&lang=0&id=0,3

2. Whitefiled â?? Kolar new BG line â?? Construction of ROB/RUB, including approach road works and other miscellaneous works from Km.40000 to 48400 between Narasapura and Kolar stations.(TWO PACKET SYSTEM)(WFD-KQZ/05)

Tender value : Rs 19.22 Crore

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=954&lang=0&id=0,3

3. Whitefiled â?? Kolar new BG line - Earthwork in embankment & cutting, minor bridges, side drains in cuttings masonry walls in platform from Km.32000 to 40000 (including Narasapura crossing station) between Narasapura and Kolar station (TWO PACKET SYSTEM) (WFD-KQZ/02)

Tender Value : Rs 23.86 Crore

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=951&lang=0&id=0,3

4. Whitefiled â?? Kolar new BG line â?? Construction of RUB, including approach road works and other miscellaneous works from Km.32000 to 40000 (including Narasapura Crossing station) between Narasapura and Kolar section . (TWO PACKET SYSTEM) (WFD-KQZ/04)

Tender Value : Rs 21.49 Crore

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=953&lang=0&id=0,3

All these tenders are having 11 / 12 months compleion time.

Also my 2nd thought on how did GOK & SWR manage to acquire so much of land in such short time between Whitefield - Kolar  

 

Krishanrajapurma Station getting upgraded

up
165 users have liked.

Krishnarajapuram: Provision of PF shelter IRS type on PF 4 for  20 Bays.

Tender work Cost :1.53 Crore,  12 Months completion,  Tender called on 12.10.2012

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=712&lang=0&id=0,3

Krishnarajapuram: Pro construction of new station building with provision of booking office, concourse, waiting hall, toilet facilities, circulating area etc.,

Tender work Cost : 1.29 Crore, 12 Months completion, Tender called on 12.10.2012

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=716&lang=0&id=0,3

 

Yelahanka station getting face lift

up
183 users have liked.

Yelahanka: Construction of new station building, Provision of PF, PF shelters, circulating area, Pay & Use toilets in connection with Adarsha Station.

Tender work cost : 1.57 Crore, Tender called 26.09.2012, 8 month for completion

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=596&lang=0&id=0,3

This is part of Adarsh station like Dodballapur, Devanhalli, Chikballapur, Yelahanka

ROB for Yelahanka new town at Allalsandra

up
158 users have liked.

Construction of Road Over Bridge including approaches in lieu of LC.No.11 at Km.15/700-800 near Allalasandra in Yeshwanthpur - Yelahanka section. (YNK-ROB/03)

Tender work cost : 19.84 Crore, called in sept'2012,  18 month completion.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=564&lang=0&id=0,3

Construction of limited height sub-way (RUB) including approaches at Km.14/800-900 near Judicial layout in Yeshwanthpur - Yelahanka section.(YNK-RUB/04)

Tender work cost : Rs 4.93 Crore, called in sept'2012,  12 months for completion.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=565&lang=0&id=0,3

 

 

ROB for Yelahanka new town at Allalsandra

up
173 users have liked.

Construction of Road Over Bridge including approaches in lieu of LC.No.11 at Km.15/700-800 near Allalasandra in Yeshwanthpur - Yelahanka section. (YNK-ROB/03)

Tender work cost : 19.84 Crore, called in sept'2012,  18 month completion.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=564&lang=0&id=0,3

Construction of limited height sub-way (RUB) including approaches at Km.14/800-900 near Judicial layout in Yeshwanthpur - Yelahanka section.(YNK-RUB/04)

Tender work cost : Rs 4.93 Crore, called in sept'2012,  12 months for completion.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=565&lang=0&id=0,3

 

 

4 more Subway to elimanate LC's on Tumkur segment

up
169 users have liked.

Baiyyappanahalli - Tumkur: Proposed subway in lieu of LCs (4 Nos) RCC Box by rolling in / launching method (Single track)

Tender work cost : Rs 4 Crore, Tender called in Oct'2012, 8 months completion

http://www.swr.indianrailways.gov.in/swr/notice/1349862670943_BACiv34_SBC_1292.pdf

Kyatasandra goods yard : Beeing moved from Tumkur station

up
160 users have liked.

Kyatasandra - Proposed goods yard arrangements by regrading of Up & down main line along with other ancillary works from Km.62 to Km.64 and Tumkur -regrading for existing line from Ch.69/800 to 72/500 and temporary diversion from Ch.71/000 to 72/100, extension of bridges retaining wall and other miscellaneous works in YPR-TK section (Additional works).(YPR-TK/91)

Tender work cost : 7 Crore, called in sept'2012,  8 months for completion.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=566&lang=0&id=0,3

Escalators for Yesvantpur station and Bangalore city

up
186 users have liked.

4 Escalaors for Yesvantpur & 2 Escalaors for Bangalore city sancion and tenders called in Dec'2012 

This info is their on Indian Railway website

ROB at ORR from MES road towards NH-4 Tumkur Road

up
154 users have liked.

This ROB tender work costing Rs 20 Crore was called in Jan'2012 and physical work has been started and looks like this may  be completed in 2 years looking at phyisical progress.

http://www.swr.indianrailways.gov.in/swr/notice/1325663641374_Item%2003%20OT-001-12.pdf

This will allow seamless train movement on Yesvantpur - Chikbanavar

Nayandahalli Station Should had some improvements

up
177 users have liked.

There should be some plan to improve Nayandahalli station for easier interchange to ORR bus stop and Namma Metro Station. Also for the proposed Light Rail.

Train fares to go up from January 21

up
163 users have liked.

The comments has been reloacted Here as a full discussion post - Admin

Note: Lets keep this post for tracking the railway works around Bengaluru, coinciding with the Namma Railu proposals. For any other railway issues, pls feel free to open new discussion threads.

Yeshwantpur Railway Station

up
176 users have liked.

I am happy to see this segment.

There is enough land next to Yeshwantpur railway station, towards Lottegollahalli, which as I have noticed, is vacant. Can somebody tell me whether this is owned by the railways or someone else? If at all it is owned by the railways, then would it not be a good idea to plan the expansion of Yeshwantpur station, or build a brand new terminus there, allowing the existing station to be a stop over station for commuter rail and the long distance trains on the Bangalore - Tumkur and Bangalore - Hassan (in future) segments??

This however, does not mean that the work on a third terminus at Byappanahalli must be stopped. Bangalore has grown so intensely that it requires multiple terminals; the scope for expanding the existing ones must be explored along with constructing new ones...

Tejaswi

Other routes within Bangalore for commuter rail

up
176 users have liked.

Guys,  I am as much an enthusiast of commuter rail in Bangalore as many of you here. Hence I intend to share a few thoughts of mine on commuter rail in this segment, which I feel has been specifically dedicated to it.

Doddaballapur - Devanahalli - Whitefield new railway line is desirable as Doddaballapur is now turning out to be the new happening residential locality of Bangalore. ITIR and Hardware park once operational would increase the number of people to and from Devanahalli, while one hardly needs to say anything about Whitefield. Hence a commuter rail network along this route would be most needed in future.

Yelahanka / Rajanukunte - Nelamangala railway line is also desirable as there have been talks of converting it into a terminus in the RITES report. Once this line is laid, besides serving commuter rail, it would also help the long distance trains from Hubli, Shimoga,  Mangalore, Hassan etc. to be terminated at Yelahanka.

Bidadi - Harohalli - Bannerghatta - Anekal town - Attibele - Sarjapur - Varthur - Whitefield new railway line would enable commuter rail, as also enable trains from Mysore towards Chennai, Salem, Tirupati etc. to avoid the ever-busy Bangalore city station, thereby creating more space for suburban trains besides enabling more long distance trains to be started from the city station.

Tejaswi

@Tejeswi, New Railway Lines!

up
166 users have liked.

Tejaswi,

The new railway lines that you mentioned in your comments are needed in long term if not today. If you read RITES 2012 report, you will find the recommendation for building a circular rail network around the periphery of Bangalore. The routes more or less connect these places

We have a big problem on our hand. GOK, state politicians have not put together a list of railway infrastructure that is needed in Bangalore and other parts of the state. In fact if you go through the Loksabha Questions, you would hardly find any demands from new line, additional infrastructure. It seems they are least interested in getting railway projects for state. Come Feb/March, they are ready for making noises as they do every year saying railways in discriminating the state. In last 5 years, only about 25 questions have been asked by state MPs to the Railway Ministry. In that City MPs draws blank. One can imagine why railways is absent in our state.

It is time we knock on our political representatives and hand them a wish list. We alone are to be blamed for state of railways in our state. Can't expect others to do our work.

In a nutshell, we the people of this state, our MPs/MLAs, our government has not demanded enough railway projects that we need. Therefore the blame squarely lie with us.

 

Some more tenders on Yelahanaka - Channasandra doubling & ROB

up
166 users have liked.

Proposed construction of Road Under Bridge in lieu of LC No.6 Km.5/800-900 size 1 x 8.25 x 4.50 RCC box and RUB in lieu of LC.No.8 at Km.10/400-500 RCC box 1x8.25x4.5 between Channasandra - Yelahanka section. (TWO PACKET SYSTEM) (YNK- CSDR/17)

Value Rs : 108876261  Date : 22-01-2013

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1052&lang=0&id=0,3

Yelahanka - Channasandra doubling project - Construction of S&T accommodation, platforms, shelter, FOB, yard drainage with passenger amenities at Yelahanka and Channasandra stations. (YNK-CSDR/19 )

Value Rs : 36480960  Date : 22-01-2013 

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1054&lang=0&id=0,3

Proposed construction of Road under Bridge 1 x 10.5 x 4.50 (Bridge proper in Railway limits only) RCC box in lieu of LC No.9, at Km.11/300-400M and Proposed construction of Road Under Bridge 1 x 9.50 x 4.00 RCC box near by LC No.10 at Km.12/500-600 between Yelahanka â?? Channasandra section.(YNK-CSDR/18)

Value Rs : 88116131  Date : 22-01-2013            

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1053&lang=0&id=0,3

Yelahanka - Channasandra doubling project - Construction of S&T accommodation, platforms, shelter, FOB, yard drainage with passenger amenities at Yelahanka and Channasandra stations. (YNK-CSDR/19 )

Value Rs : 36480960  Date :  22-01-2013

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1054&lang=0&id=0,3

Station Lighting and Electronic Interlocking System @ Tumkur

up
150 users have liked.

Electrical arrangements in the platform shelters and raised /extended platforms at various stations in Bangalore Division

Value :  Rs 30 Lakhs

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1027&lang=0&id=0,3

Design, supply, installation testing and commissioning of Electronic Interlocking System (EI System) at Tumkur station of Bangalore division in connection with New Line between TK-RDG Section.

Value Rs : 1.35 Crore  Date : 19-01-2013

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1031&lang=0&id=0,3

So Tumkur  is getting developed as good junction and SWR should take up electrification on this Tumkur - Chikbanavar soon

 

Kengeri Station getting PF shelters

up
187 users have liked.

Kengeri Station :

Kengeri: Provision of PF shelter on PF 2 & 3 IRS Type 6 Bays SW-II Provision of PRS building at First Floor & Extn of two wheeler parking.

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1125&lang=0&id=0,3

Tender Work Value : Rs 62.2 Lakhs

Banswadi Station :

Provision of Second Loop with CSL of 715 mtrs. with high level platform of 540 mtrs at BAND station in YPR-SA section of Bangalore Division

http://www.swr.indianrailways.gov.in/TenderDetails_cpp.jsp?T_ID=1164&lang=0&id=0,3

Tender Work Value : Rs 36.51 Lakhs