RITES - CRS implementation in 3 Phases

Three Phases

RITES report has divided all the works that are needed for CRS into 3 Phases. The Phases are 1A, 1B and 2. Each of these have been identified with slew of works to be carried over, cost of works and the time frame to complete the works.

RITES - Capacity Enhancement Strategies

Section 5 - Capacity Enhancement Strategies

Bangalore - SBC Terminal

  • Shifting 4 Pit lines to Binny Mills land
  • No terminal or shunting operations
  • Universal dispatch/receiving facilities
  • Platforms to be full length
  • Trains to go in all directions (YPR to MYS and BYPL, MYS to YPR, BYPL, BYPL to MYS, YP

Public discussion on a Commuter Rail Network for Bangalore

15 Jul 2012 10:30
Asia/Calcutta
Commuter Rail

Hasiru Usiru, along with PRAJA, ITEC (IT Employees Centre) and Concern (IISc), is organizing a public discussion on a Commuter Rail Network for Bangalore (Namma Railu) on 15th July, Sunday, 10.30 AM at SCM Hall, Mission Road.

Praja Commuter Rail presentation @ OneBengaluru

Commuter Rail
8 Jul 2012 15:00
8 Jul 2012 17:00
Asia/Calcutta

Sunday 8th July 2012, 3PM @ 1677 17th Main, J.P.Nagar 2nd Phase, Bangalore,

Other Commuter Rail Study reports for Reference

Commuter Rail

Hidalgo County Commuter Rail Study

http://www.co.hidalgo.tx.us/DocumentCenter/Home/View/14006

On Page 207 : Public meting held to take opinion of the Public.

Commuter Rail - Email Campaign !

Commuter Rail

RITES report is out. Time for action. Shouldn't take more than 5 minutes to send one. Here is a sample of the email that I had sent to various people. You may send this petition to these email addresses:

Government Of India

Union minister of Urban Development - Minister-mud@nic.in

Union minister of Railways - mr@rb.railnet.gov.in

Summary of June 2012 RITES draft report on CRS

In June 2012, RITES submitted a draft report on feasibility / go forward details on commuter rail service (CRS) for Bengaluru to DULT. Here is a summary and abstract of relevant portions of this report. The report is also available in full at this link.

Will you take part in an on-street event in support of Commuter Rail?

RITES report on Implementation of Commuter Rail for Bengaluru

Commuter Rail

The draft report of the Implementation of Commuter Rail for Bengaluru has been released by RITES to DULT. DULT has shared the report with us for our comments. We are expected to profvide our feedback before 30th of this month. SO do leave your feedback as comments to this thread. 

 

Controversy brewing over commuter rail, Metro to blame?

Commuter Rail

Time to indulge in some talk on Namma Railu aka Commuter Rail Service (CRS). RITES has submitted a report to DULT last week. Sources claim that Rs 3000-4000 Crore can give Bangalore a 15 minute lead time commuter rail system covering 200 odd kms of distance. We will validate this once the RITES report is made public.

Praja.in comment guidelines

Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!