I am reproducing below a letter a friend had mailed to BMTC MD (bmtcmd@gmail.com):
January 2012
Yesvantpur - Yelahanka Doubling held up due Land not provided by GoK
Here you can see the reply to RTI application on
1. Yesvantpur to Yelahanaka ( 12 Kms ) is penidng due to Land not provided by GoK.
2. Yelahanka - Channasandra ( 12.9Kms ) tenders finalised but work not yet started.
3. Kolar - Chikballapur ( 96.5 Kms ) expetected to be completed in 2011-12.