Construction progress during June 2007
Work at the new Bangalore Airport has now reached 77% completion. This month marks the completion of two years since the construction work started at the site in June 2005. During this time, the area has been completely transformed and all the airport facilities are clearly visible. Following is the construction, engineering and procurement update as of June 2007
Terminal Building
Airside Works
Other buildings & infrastructure
Concessionaire works |
Source www.bialairport.com
Official Updates of Construction during July 2007
The construction of new Bangalore Airport has now reached the 26th month starting August 2007. The total project progress is now approximately 80%.
Highlight The Terminal building Most works are now at various stages of completion. Completed works include the roof, the front and back glass façade and the side walls. Additionally, within the terminal building the installation of the escalators, structural supports for the glass elevators, structural steel works for the retail and duty free concessionaires, structural works for the baggage handling (departure area) and the installation of the three carousel structural supports is complete. Activities in progress include the granite flooring works, the granite cladding of the columns, installation of boarding bridges, installation of the fixed link bridge connecting the terminal building, installation of the fire alarm detectors and the light fittings. Airside Works The runway is entirely complete as of April 2007 and the Air field lighting cabling works are nearing completion. The paving works at the taxiway is now complete. On the apron area, laying of the concrete layer is completed for 52% out of 381,000sqm, this includes the isolation bay.
Other buildings & infrastructure Concessionaire works update
* At the fuel farm, the construction of all the buildings is completed
and the finishing works are in progress. Installation of the electrical
and mechanical system equipment continued. The laying of the feeder
line connecting the fuel farm and the apron are in progress. At the
apron, installation of the hydrant pipelines continued. |
source: bialairport.com
New! Oct 2007 Images Of BIAL!!
New! Oct 2007 BIAL Airport City, Plans & Renders!!
Construction progress update for September 2007The opening of the new Bangalore International Airport draws closer with just 6 more months to go. Progress on the project is now approximately 85%. In addition to the runway being complete, the taxiway has also been completed. At the terminal building, all the civil works are now done and finishing works are in progress.
The Terminal Building
- The installation of the eight fixed link bridges connecting the terminal building and the apron is now complete. Additionally, in the baggage handling areas, the electrical and instrumentation works are nearing completion. The commissioning activities for these areas are due to begin shortly.
- Installation work of the glass elevators, escalators, the automatic doors for entry and exit into the terminal building is now being carried out. Work on the installation of fire alarm detectors and the light fittings continued.
- At the duty free area, the site handover to the food and beverage concessionaire was achieved this month. Other construction work for the retail shops continued.
- At the car park area in front of the terminal building the final paver block installations are progressing. The landscaping works within this area continued.
- The installation of the light poles along the main access road and the car park is in progress. 60% of the light poles have been installed.
Airside Works
- The installation of the approach lights and the flash lights on the east and the west side of the runway are completed and the installation of taxiway lights is now in progress. Work on the airside wall illumination is progressing at a good pace; currently 310 light poles out of the total 323 poles have been installed. Cabling works are now in progress. On the Apron area, laying of the final concrete layer is nearing completion.
Other buildings and Infrastructure
- The earthwork for the main access road outside the boundary wall is nearing completion.
- Construction of the trumpet interchange connecting NH7 to the airport is in progress. The earthwork, foundation concreting work, column concreting work and the pre-cast retaining wall work is ongoing.
- At the Air Traffic Control (ATC) tower, the aluminium composite panel (ACP) cladding and glass fixing works are nearing completion.
- The elevator installation works in the ATC tower and the ATC block are nearing completion.
- The installation of the pumps and other equipment in the sewage treatment plant and the pump houses continued.
- Nav- Aid (navigation aid) buildings: At the Radar Tx building, the final finishing and electrical works are in progress. All the other Nav-aid facilities such as the localizer buildings, the DVOR building, the frangible and the non-frangible buildings are completed and are ready for inspection.
BIAL began construction of the new Bangalore International Airport on 2 July 2005. The construction is progressing on schedule and BIAL will open the airport for commercial operation in April 2008.
Construction progress update for November 2007
Trial runs will begin at the new Bangalore International airport in December 2007. These trials to be held in three stages i.e. basic, advanced and integrated will finally conclude closer to the airport opening date on March 30, 2008.
The construction and infrastructure advancements at the airport project site continued and are now in the concluding stage. The commissioning of various equipments continued i.e. all the airfield lights at the runway and taxiway, passenger boarding bridges, the baggage handling system and the escalators at the terminal building.
The commissioning phase also commenced at the Air Traffic Control (ATC) block. Other commissioning work included the street lights, cable checks at the airside service road and the secondary access roads.
The Terminal Building
- The finishing works in the terminal building continued with the installation of the internal glass partitions, handrails and the external aluminium panel cladding (ACP). Other work within the terminal building included the construction of the duty free areas, cabling work at all the CUTE (common user terminal equipment) check-in counters, the installation of the public addressing system, the CCTV cameras, the antennas and the light luminaries.
- The construction of the car park opposite the terminal building is in progress. Lying of the paver blocks and landscaping in this area continued.
Airside Works
The major concreting works in the airside administration building are completed. The landside and airside landscaping works are now in progress.
Other buildings and Infrastructure
The construction of the airside perimeter road and the main access road till the trumpet interchange is in progress. The grading and road construction works around buildings and various installations are in progress.