BIAL - Opening Dates

From BIAL website: - All flights scheduled to depart after 00:01 on 30th March,2008 will operate from the New Bangalore International Airport. - Arrival flights on 29th March, 2008(after 20:00) may land at the New Bangalore International Airport or HAL. Please contact airline. some updates...

BIAL Official Updates September 2007

New! Oct 2007 Images Of BIAL!!

New! Oct 2007 BIAL Airport City, Plans & Renders!!

Construction progress update for September 2007

The opening of the new Bangalore International Airport draws closer with just 6 more months to go. Progress on the project is now approximately 85%. In addition to the runway being complete, the taxiway has also been completed. At the terminal building, all the civil works are now done and finishing works are in progress.

Let us ask BDA/BBMP?

Our long term goal at Praja is to do more than blogs and discussions. For that, we first have to grow into a larger community of like minded concerned residents of this city. While we are not there yet, how about we try this experiment on the subject of alternate routes from Bannerghatta Road to Hosur Road.

What we need is a good connection somewhere between NICE Peripheral Road and Outer Ring Road. For a start, how about we post a suggestion cum question to BDA/BBMP, and do it this way:

- frame one short and precise paragraph on this - find email id or sarkaari website where we could post this - at least 20-30 of us will post this exact query

Some Photos of Where the Road Ends

A complete dead end to all the work.
Here are some photos of where the Road really ends. If this would have continued, then it could have been connected to the BTM road which goes just beside the lake.

Bannerghatta Road Alternatives

Exploring ideas about a radial corridor from BTM layout to points further south. This corridor will act as an alternative to Bannerghatta and Hosur Roads.

BIAL Official Updates August 2007

Official Updates of Construction during July 2007
The construction of new Bangalore Airport has now reached the 26th month starting August 2007. The total project progress is now approximately 80%.

BIAL Updates July 14 2007

Key BIAL Concessionaires

  • Aviation Fuel Facility: Skytanking & IndianOil
  • Ground Handling: GlobeGround India & Air-India/Singapore Air Terminal Services (SATS)
  • Cargo Facility: SATS/Air-India & Bobba Group/Menzies Aviation

 

BIAL Dedicated Rail

BIAL to invest in the high speed rail to the airport. Interestingly the rail connectivity to cost more than the airport itself.

BIAL May Pilot Rail Link To Devanahalli Airport

BIAL Updates July 13 2007

A summary of the developments so far. Check the links for context.

Second BIAL runway by 2013: Brunner
Text Source: Bangalore, DH News Service updated with relevant links.

BIAL Official Updates July 2007

Construction progress during June 2007

Praja.in comment guidelines

Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!