The below picture is of the road works which have started this week on MG road. As can be seen,the exisiting concrete blocks have been removed an neatly piled up on the road..this will most probably be recycled on the same footpath eventually in the coming days.
The same road was done up just before the GIM which happened last month.
- What was the great hurry that this works had to be taken up within such a short time?
- Did the foot path go so bad that it needed rework so fast?
- There is TenderSURE road project approved on this road and is supposed to start soon..why this current rework being taken up before that?
There are various such questions which crop up. Probably an RTI will provide us information on the money being spent on this project as well as the one done few weeks earlier for the GIM.
BBMp tried unsuccessfully to address this 'unwanted' tender contracts issue by bringing an internet site having list of all the works (road history) few months ago.. http://218.248.45.164:8080/BBMPCitizen/#/MainPage.xaml
However this site does not have much records at all.
Such unwanted road 'projects' are routinely undertaken accorss the city just with one intention. And this is very visible.
Wish someone can put a stop to this criminal drain of resources!
Comments
BMRCL pays..thats why..
more here
So they had to start with MG road which is slated to be done up under TenderSURE specs too?? Why the blatant lies??
Theres absolutely no accountability of any sort with money being splurged on unwanted projects!
work status <update>
work has come to a stand still..NAPC the contractor has moved in some concrete blocks and they are done with the funds I guess..
Another tactic in BBMP to milk the exchequer..start works and stop midway stating approved funds all spent up and will ask for more..the BBMP mafia 'approves' the extra payment when there is some public outrage on the undone work..
What's New?
What is new here? Roadwork and footpaths are the cash cows for all people involved. That’s pretty much well known. How many footpaths are walkable? Footpaths are like drain slabs. The stones cover the drains in a haphazard manner with that are cemented to each other. Even the cement that connects the slabs looks like a pyramid.
BBMP is buildingĀ Light
more here
Now this is the diluted version of tenderSURE..or is it?
What is TenderSURE is about:
The above points are from BBMP itself. However looking at the work being done on MG road is some what complies to the part of the second point only. Again no 'broad' footpath as claimed, its been the same size as it was before. So how can it be even called TenderSURE 'light'??
This is surely a money making exercise especially in the light of MG road being identified for TS roads in the 3rd phase of implementation!
tenderUnsure
More appropriate to call it "tender unsure" than "lite tenderSure". The whole concept seems to have been hijacked by the BBMP johnnies to suit their interests.
its Jayanagars turn.,.
more here
All that is needed is a good record of all the public works that BBMP is upto at any given point in time, so that the repeat of such incidents do not occur. There needs to be transparecy and thats a desparate need.