Majority of Construction contracts Tenders were suppose to be published during Q2/ Q3 and Q4 of 2013-14 and balance works contract tenders to be called during Q1/ Q2 / Q3 / Q4 of 2014-15
Alos Road widening and Road Streangthening , Demolution of properties Tenders were to be called during Q3/Q4 of 2013 -14
http://bmrc.co.in/pdf/phase2/phase2contract.pdf
Considering above plans and actual approval given in Jan'2014, project was already running behind schedule.
With almost completing one year since approval Jan'2015 for Ph-2, on the ground has any work started or Tenders awarded by BMRC ???
That means we will get the Ph-2 services available soe where during 2019-20. With further BBMP increasing guidence value and new land act effect fro 1st Jan'2014, PH-2 project will get extended in completion and cost fro Rs 26,000 Crore.
Only Construction Tender for Mysore side during June'2014 :
Tender Notification for Construction of Elevated Structures of Length 3.945 km (approx) from Mysore Road station dead end to Pattangere Station including 4 Nos. of Elevated Metro Stations viz Nayandahalli Station, Rajarajeshwarinagar Station, Jnanabharathi Station and Pattanagere station in the extension on west side of E-W Corridor of Bangalore Metro Rail Project, Phase-2,
Posted on 30/06/2014
Comments
Preliminary notifications issued for land acquiring
With increase in guidence value by BBMP during Sept'2013 and Nov'2014, with further new act for acquiring fro 1st Jan'2014, these will have ipact on cost and time.
http://bmrc.co.in/pdf/news/Nov-14.pdf
Already costs have been estimated for Ph-2 based on 2010 prices, even considering 5% escalaltion, revised cost should be calculated by BMRCL before starting actual work.
Also how much funding received for Ph-2 work till now ???
Namma Metro Phase II to be Realigned at 2 Stations K R Puram
A section of Namma Metro Phase-II will be realigned due to land acquisition issues and the presence of a railway line in the vicinity. The changes will be effected at two stations that figure in the Byappanahalli-Whitefield elevated corridor, which is an extension of Reach-I from MG Road to Byappanahalli.
According to the new proposal, Narayanapura metro station will be knocked off the network and Krishnarajapuram metro station will be shifted by 295 metres. These stations figure in the 15.5-km line from Byappanahalli to Whitefield.
“The plan changes were okayed during a high-powered committee meeting with the chief secretary at Vidhana Soudha,” said a highly-placed source.
“It is very difficult to acquire land in that area. Moreover, the K R Puram railway line runs on one side of the proposed Reach-I extension. It will not be possible to link the entry on this side of the line with other Metro-related infrastructure on the other side by building stairs. Hence, we have decided to remove Narayanapura from our network and slightly shift the K R Puram Metro station to the left,” the source said.
The deadline for acquiring land for Phase-II has been fixed as April 2016.
Phase II Details
Phase II (72.1-km long) is an extension of all the reaches of Phase-I, in addition to two new lines.
It is slated to cost Rs 26,800 crore and is expected to be completed by 2020.
This involves extending the East-West lines of Mysuru Road to Kengeri and Byappanahalli to Whitefield and the two North-South lines from Puttenahalli to Anjanapura and Hessaraghatta Cross to Bengaluru International Exhibition Centre. The two new lines would be from R V Road to Bommasandra (East-West) and from Gottigere to Nagawara (North-South).
This particular extension of Phase II, the longest of all the four extensions, is awaited eagerly as it is slated to provide relief to employees in the IT corridors of Whitefield and Electronics City. The service from Byappanahalli will pass through Jyotipura, Krishnarajapuram, Mahadevapura, Garudacharpalya, Doddenakkundi Industrial Estate, Visveswaraya Industrial Estate, Kundalahalli, Vaidehi Hospital, Satya Sai Hospital, ITPL, Kadugodi Industrial Area and Ujwala Vidyalaya before terminating at Whitefield.
http://www.newindianexpre...
If this is the progess of METRO, Expert team who prepared DPR for Ph-2, they did not sea this and how did the GOK and BMRC board approved it in first place ???
Or is it some individual loosing land so change the station.
In whole thing, BMRC and DPR Constultant have messed it by not considering how to integrate KR Puram Railway Station, BMTC and METRO with Auto & Taxi stand.
If now things are not done in detailed and funds r not allocated, K R Puram area will be mess like KR Market in future.
As such BMRC does not share any info with public how KR Puram station will be integrated with other modes of transport. GOK wake up and its tax payers money you are spending and be accountable.
no station at lowry memorial?
There was land acquisition issues at Lowry memorial and lots of families were affected at Narayanapura stn..so what does BMRCL do?
It quits both places and moves the station to somewhere near Whitefield Honda showroom now(I guess)..which is almost in the middle of no where..its not near at all to KR puram station nor is it catering to total residential areas!
Good, this is as per BMRCL track record!
here is the new station..
hoodi u turn not shown correct in the image!
ನಮ್ಮ ಮೆಟ್ರೋ ಸಂಪನ್ಮೂ ಲ ಕ್ರೋಡೀಕರಣಕ್ಕೆ ಹುಡುಕಾಟ
"ನಮ್ಮ ಮೆಟ್ರೋ' ಯೋಜನೆ ನಿರ್ಮಾಣ ಮಾತ್ರ ಸಮಸ್ಯೆ ಅಲ್ಲ. ಯೋಜನೆಗೆ ಬೇಕಾಗುವ ಆರ್ಥಿಕ ಸಂಪನ್ಮೂಲ ಕ್ರೋಡೀಕರಣ ಕೂಡ ಸವಾಲಾಗಿದೆ ಎಂದು ಅಸಹಾಯಕತೆ ವ್ಯಕ್ತಪಡಿಸಿರುವ ಬೆಂಗಳೂರು ಮೆಟ್ರೋ ರೈಲು ನಿಗಮದ ವ್ಯವಸ್ಥಾಪಕ ನಿರ್ದೇಶಕ ಪ್ರದೀಪ್ಸಿಂಗ್ ಖರೋಲ, ಸಂಪನ್ಮೂಲ ಕ್ರೋಡೀಕರಣಕ್ಕೆ ಹೊಸ ಮಾರ್ಗಗಳನ್ನು ಹುಡುಕುತ್ತಿದ್ದೇವೆ ಎಂದು ಹೇಳಿದರು.
ಕರ್ನಾಟಕ ವಾಣಿಜ್ಯ ಮತ್ತು ಕೈಗಾರಿಕಾ ಮಹಾಸಂಸ್ಥೆ (ಎಫ್ಕೆಸಿಸಿಐ) ನಗರದಲ್ಲಿ ಮಂಗಳವಾರ ಹಮ್ಮಿಕೊಂಡಿದ್ದ "ಮೆಟ್ರೋ ಯೋಜನೆ ಹಂತ-1 ಮತ್ತು 2ರ ಪ್ರಗತಿ' ಕುರಿತ ಸಂವಾದದಲ್ಲಿ ಅವರುಮಾತನಾಡಿದರು.
ಸುರಂಗ ಕೊರೆಯುವುದು, ರೈಲ್ವೆ ಸುರಕ್ಷತಾ ಆಯುಕ್ತರಿಂದ ಅನುಮೋದನೆ ಪಡೆಯುವುದು ಒಂದು ರೀತಿಯ ಸವಾಲು. ಆದರೆ, ಇದರೊಂದಿಗೆ ಯೋಜನೆಗೆ ಸಂಪನ್ಮೂಲ ಕ್ರೋಡೀಕರಣ ಕೂಡ ಬಹುದೊಡ್ಡ ಸವಾಲಾಗಿದೆ. ಸುಮಾರು 13 ಸಾವಿರ ಕೋಟಿ ರೂ. ಮೊದಲ ಹಂತದ ಯೋಜನೆಯು ಹಣಕಾಸಿನ ತೊಂದರೆಯಿಂದ ವಿಳಂಬವೇನೂ ಆಗಲಿಲ್ಲ. ಆದರೆ, ಎರಡನೇ ಹಂತದ ಯೋಜನಾ ವೆಚ್ಚ ದುಪ್ಪಟ್ಟು ಅಂದರೆ 26,500 ಕೋಟಿ ರೂ. ಆಗಿದೆ. ಇದು ಈಗ ನಮ್ಮ ಮುಂದಿರುವ ಸವಾಲು ಎಂದರು.
ಈ ಸಂಬಂಧ ಫ್ರಾನ್ಸ್ ಮೂಲದ ಬ್ಯಾಂಕ್ ವೊಂದರಿಂದ ಈಗಾಗಲೇ 2 ಸಾವಿರ ಕೋಟಿ ರೂ. ಸಾಲಕ್ಕಾಗಿ ಒಪ್ಪಂದ ಮಾಡಿಕೊಳ್ಳಲಾಗಿದೆ. ಜರ್ಮನ್ ಮೂಲದ ಕೆಜಿಡಬ್ಲ್ಯು ಜತೆಗೆ ದೀರ್ಘಾವಧಿ ಸಾಲಕ್ಕಾಗಿ ಮಾತುಕತೆ ನಡೆದಿದೆ. ದೇಶೀಯವಾಗಿ "ಮೆಟ್ರೋ ಬಾಂಡ್'ಗಳ ಮೂಲಕವೂ ಸಾವಿರ ಕೋಟಿ ರೂ. ಕ್ರೋಡೀಕರಿಸುವ ಗುರಿ ಇದೆ. ಅಲ್ಲದೆ,
ದೇಶೀಯ ಹಣಕಾಸು ಸಂಸ್ಥೆಗಳಲ್ಲಿ ಮೂಲಬಡ್ಡಿದರ ಕಡಿಮೆಯಾಗಿದೆ (ಉದಾ: ಎಸ್ಬಿಐ ಶೇ. 9.5). ಅಲ್ಲಿಂದಲೂ ಸಾಲ ಎತ್ತಲು ಯೋಚಿಸಲಾಗುತ್ತಿದೆ ಎಂದು ಮಾಹಿತಿ ನೀಡಿದರು.
http://www.udayavani.com/...
Long way to go for Ph-2 loan arrangment. I will be happy if BMRCL can arrange loan for the Ph-2 by next 5 years itself forget about the completion.
Cantonment station and Cantonment METRO station have no links
Once again how Govt agencies in Public services work in isolation : BMRCL is locating Cantonment station at distance from the existing Cantonment Railway station. Railways are in a hurry to lease out 2 Acers of Land for PPP without any expansion of Cantonment station and considering METRO interchange, if this Bannerghata - Nagawara to be extended to Airport. As usual BBMP is busy calling tenders for its Corporaters wishes to be filled. If this is way, Bangalore will never get good multi modal transport hubs
PH-2 METRO alignmnet as per BMRCL website
As per Railways Land 2 Acers leasing for PPP without any METRO considerations
BMRCL wants to extend the Bannergahatta - Nagawara line to Airport, no plans for integration at Cantonment station.
BMRCL 2013 Press release about linee extension still in drawing board