Skip to Content

New completion date for Kadugodi flyover!?

up
264 users have liked.
Infrastructure

See Page 18, Times of India - December 26,2009, SOUTH WESTERN RAILWAY (ROB-WFD-57R)

LINK FOR THE Same on the epaper:

http://epaper.timesofindi...

I think this is the balance work thats needs to finish the flyover and mentions the time period as 4 months from Jan end.(Think thats when the tenders get awarded).I think the pressure from the work group has helped.

AttachmentSize
Kadugodi SWR Tender Dec 09.jpg130.38 KB

Comments

murali772's picture

one hopes so, but - -

up
210 users have liked.

Looks like it, alright. But, what is surprising are

1) Was this major bit left out of the original tender?
2) If it had indeed been included, which is more likely, what has caused the re-tendering now?
3) Who is responsible for this inordinate delay, and consequent costs?
4) Why were the people concerned sleeping over it, till the public started mounting pressure?
5) Has the Railways, and other bodies involved, learnt any lessons?
6) And, most importantly, why are the Railways (as also the other concerned bodies) not giving updates on the project, on their own?

Well, going by the experience, the re-tendering doesn't mean the job will be over in the next four months allocated for completion. Perhaps the team here needs to closely monitor the progress to ensure that there are no further hold-ups.

Muralidhar Rao
Muralidhar Rao
mbhatia's picture

Both Good and Bad news

up
223 users have liked.

This retendering appears to be both Good and Bad. Good in the sense that work has restarted which was dead for last 6-8 months. But bad in the sense that it may be more delayed than 4 months from Jan end stipulated in tender period.

adityaselect's picture

whats next ?

up
196 users have liked.

Initially thoughts were to wait till Jan 19 and after that monitor the progress. But on second thoughts, this tender is NO assurity of flyover completion but to another 1+4 months delay under best case.

I think group should continue as before instead of waiting and monitoring.

Two questions that authorties needs to answer are:

1)Why Mr Agarwal gave a 31dec as completion of flyover ?

2)When will it complete ?

-Thanks

-Thanks

silkboard's picture

Here is that tender

up
198 users have liked.

Since the epaper link may not work, this is what Raghu is talking about.

mbhatia's picture

Plan of Action

up
214 users have liked.

Happy New YEar to all.

So what is the next plan of action on this ROB? Do we need to meet with some officials or drop email to some other officials?

 

Regds,

manish

srgopalan's picture

Additional work

up
187 users have liked.

 It is surprising to see that the value of the tender is quoted as close to  Rs. 3.12 crores which means it is quite a major work pending. It is not clear what the scope of work for this tender is. Looking at the project duration of 4 months, assuming further delays, there is no way the bridge will be ready before next rains in June.

Any suggestions to speed up the project?? 

sanjayv's picture

Pressure through RTI?

up
203 users have liked.

One suggestion would be the following

1. Fire off an RTI later this month suitably drafted which asks for - Name and address of contractor, All milestones of new project and dates of completion, detailed budget split  for various phases of completion (just for the heck of it) and contact information of the officer who can provide updates

2. At one month intervals, fire off additional RTIs (if required) asking for status updates on each of the milestones as of a certain date and reasons for any delays.

3. That should apply some pressure.  Plus it gives us detailed documented evidence which will be informational and will have other uses in the future,

What say?

silkboard's picture

mbhatia, others, meet for RTI?

up
219 users have liked.

As Sanjayv suggests,shall we file at least 1 RTI to get started. We will repeat the RTI on 1st of every month. That should keep the pressure.

Who will we mail the RTI to? SWR only?

Also - which MLA's constituency does the bridge fall in? If another person can come forward o help, I can share the onus of calling around to arrange a meeting.

silkboard's picture

Lets meet at the site itself - Jan 16th morning?

up
199 users have liked.

I prefer Saturday Jan 16th morning. But if at least 3-4 can meet today evening itself (or, a weekday evening 5.30 PM types), can meet and do this:

  • Take pics of work progress and post
  • Finalize the RTI application
  • Plan meeting local MLA or SWR officials

RTI app can be finalized on the website itself via these posts and comments.

 

sanjayv's picture

Is this tender still open?

up
193 users have liked.

 I cannot seem to find it on the tender websites.

mbhatia's picture

Meet

up
223 users have liked.

Guys,

Let us meet on 16th Jan at around 11:00 AM at the flyover site itself. I can meet before that to discuss the RTI. Since I have never done filed RTI before so we if someone who is already aware of the process can help then it will be great.

Let us pump up the pressure so that this issues doesn't go to backburner again.

 

Regds,

manish

silkboard's picture

okay, let us meet in person - Jan 16

up
207 users have liked.

I will be there. I am on a low speed line rt now, can someone post an "event" for this meeting please.

sanjayv's picture

I posted an event for you SB

up
201 users have liked.

 Not sure if I can commit to come on Sat yet.  But will try my best.

sanjayv's picture

Citizen matters article on Whitefield ROB

up
199 users have liked.

 Vaishnavi very kindly posted the link to a citizen matters article on the topic.  I am adding a link here for cross referencing here.

 

mbhatia's picture

Saturday meeting

up
219 users have liked.

Hi,

Are we meeting this saturday and at what time? How many confimed attendees are there?

 

Regds,

Manish

sanjayv's picture

Manish, event has been posted

up
211 users have liked.

 Hi Manish, 

There is an event that has been posted.  As far as I know, there are three confirmed attendees, including you.  Others are Pranav aka Silkboard and PSA sir.  I am a maybe.  Time, as agreed is 11 am.

 

Event notice is here.

silkboard's picture

11 am, Kadugodi bus stand

up
200 users have liked.

Not sure if all saw the event posted separately. Looks like 3-4 of us are going to be there. See you all at 11 AM, Kadugodi bus stand.

sanjayv's picture

Meet photos

up
208 users have liked.

 SB and I met up near the bridge and did a walk about.  Here is a google map along with some placemarks and photos attached to the placemarks. View the placemarks in the map to see links to photos. Interesting, this is a tiny 2 lane bridge!  I bet it will get choked once it finally opens.

From all the Citizen matters articles, it looks like essentially the new tender is meant to sort the remaining work.  The key pieces is to get the girder certified, drop it in place, Finish the road work on the approach as well as road on the bridge.

The key question is how to track the progress of the new project.  Citizen matters is certainly on that project. We can add our voices to keep the pressure on. More on an RTI approach in the next post.

 

 


View Kadugodi

sanjayv's picture

RTI questions for the bridge

up
200 users have liked.

 My first cut. Please feel free to edit/modify/comment

1. Who is the new contractor assigned to finish the Kadugodi ROB (Provide location, Tender number etc.).  What is their address and contact information?

2. What is the new schedule for completion of the project with Milestones and a scheduled date of completion of each milestone

3. Please provide contact information of official in the railways who can provide us status updates on this project.

 

The one thing I am not clear about is where to file the RTI.  SWR website has a list of PIOs, but no clear description of the process to file. I am worried as to getting stuck in procedural wrangles on whether we filed correctly.

The Indian Railways website has a detailed description of RTI filing along with e-tracking! See the link.

mbhatia's picture

RTI questions for the bridge

up
185 users have liked.

Hi All,
The questions posted by Sanjay seems to address majority of open items.

We need to also find out the penalty rules to be applied if project is not completed in time and absolute max time it will take. Because all tenders have time for completion and then the max time to which it can be stretched with light penalty clauses.

Also need to find out details on the width and reasoning behind it being such a narrow bridge.

When I was talking to SWR PIO 3 weeks back he was asking for RTI # based on which he will disclose information.

Regds,

manish

mbhatia's picture

Citizen matter Updates

up
224 users have liked.

 The link to tender is below:

http://tenders.gov.in/innerpage.asp?choice=tc5&tid=karn266661&work=1

 

The tender will be opened tomorrow at 3:30 PM.

As per new information posted on Citizen matter :

18-Jan, 09 AM] Subramaniam Vincent

A reader Narayanan has posted this comment on our earlier Nov 2009 article on 'Second life for Whitefield Bridge'

[18-Jan, 08 AM] Narayanan

Inidan Railways has given a new tender for Rs.Rs 3,12,08,698/- for the same. From the tender it looks like they have dropped the idea of gridder and are going in for a RCC structure. I think we cannot expect a new completion date in anytime less than 1 year.

sanjayv's picture

concrete bridge?

up
219 users have liked.

 I quickly went through the tender documents.  The cost was revised as per a corrigendum to 2,86,92,196/-

It is still a steel bridge for the main span over the railway line, so there is no change in design.

The SWR PIO needs an RTI# to disclose information?  What new rule is this?  The government is supposed to release information to the public.  The RTI is just a formal route for when one has to assert legal rights!

Manish - can you find out from the SWR PIO exactly how and where to file this RTI?  Do we file it with IR or SWR?  In Whose name should the Rs 10/- DD/postal order be drawn.  What address should it be sent to? I have looked all over online, but there is no info on this part.

The reason for asking is that the Indian railways website has explicit instruction for directly filing it in Delhi and all kinds of dire warnings to use the right address and right beneficiary of the Postal order in order for the RTI to be accepted (avoiding delays).  If we send it to Delhi, it will take a while for the file to come to the concerned department.

 

 

kbsyed61's picture

@Sanjayv, Here is RTI applying Info for SWR!

up
217 users have liked.

Sanjay,

Address your RTI application to:

Shri. A.Balachandar
CPRO & PIO,
H.Q. Office, S.W. Railway
Hubli-580023


Make the Post Order / Demand Draft for Rs.10/- Payable to

“Pay and Accounts Officer, Railway Board”.

Link for further Information on Indian Railways RTI:
http://www.rti.railnet.gov.in/default.asp

sanjayv's picture

Thanks Syed

up
190 users have liked.

I had gone through the RTI website, but missed this address.

suryakamal's picture

Any news on Tender?

up
200 users have liked.

Gentlemen,

Any news on the Tender?

Wondering, with monsoon too stepping in the next 4 months, when are we going to see the gap bridged?

Passing through this junction everyday reminds me of Sandra Bullock / K Reeves of Speed movie!  Only they can use the bridge in the current condition !!

Regards....Surya

mbhatia's picture

Any Updates

up
209 users have liked.

Hi Sanjay/Pranav,

Do you have any updates on tender and to whom it has been allocated? This was supposed to be opened on 19th Jan. Do we need to file RTI for this information also?

 

This bridge is mentioned in TOI today in mahadevpura BBMP limits as one of the pain points in otherwise well developed Mahadevapura and as per that article construction will start in Feb after tender allocation.

 

Regds,

Manish

adityaselect's picture

No bidders ?

up
191 users have liked.

HI,

I am not able to search this tender any more. Earlier it use to appear under Tender By location with search key 'whitefield'.

However the link still works
http://tenders.gov.in/innerpage.asp?choice=tc5&tid=karn266661&work=1

I am guessing there were no bidders !!

Thanks !

-Thanks

Naveen's picture

Steel Girders for Kadugodi Flyover ?

up
212 users have liked.

A few days back, I saw a long trailer truck, loaded with two long, reinforced steel girders, parked at BEML gate (off Suranjandas road). I asked the driver what these were & he wasn't sure, but had stated that he had to deliver it at whitefield at late night (when traffic was low). He had stated that directions /address were with some official who would be escorting him there.

I think these were for the Kadugodi flyover. Can anyone confirm if the steel beams (painted yellow) have arrived at the site & are being put in place overhead, across the tracks ?

sanjayv's picture

Pranav, can you file an RTI

up
187 users have liked.

 Hi Pranav,

As discussed earlier, can you file the RTI for this?  Here is a text and the place where I think we should file. I think we should file directly to the Railway board in New Delhi.  Even if we do send to SWR, I think the application is sent to New Delhi for creating a file and scanning into their system.

 

So here goes.

To

Chief Public Information Officer, Railway Board

No. 5, RTI Cell, Rail Bhavan, Rafi Marg

New Delhi 110 001

Dear Sir/Madam,

This is with regards to the rail over bridge (ROB) being built at Kadugodi near Bangalore at LC No. 132 near Whitefield Railway Station. The ROB work is currently stalled. A new open tender for the balance work was issued by SWR on 23/12/2009. The tender notice number is CAO/CN/BNC/66/09

Kindly provide the following details on this project

 

1. Who is the new contractor assigned to finish the Kadugodi ROB? What is their address and contact information?

2. What is the new schedule for completion of the project with detailed milestones and a scheduled date of completion of each milestone.

3. Can you provide contact information of an official in the railways who can provide periodic status updates on this project to the affected public without having to file fresh RTI requests..

 

Yours sincerely,

XXX (Name and address)

 

Please make payment of Rs. 10/- payable to "Pay and Accounts Officer, Railway Board, New Delhi"

Approximately one week after sending application, we should be able to get a case number to access information online.

I am avoiding the width of the flyover question here so that we do not have un-necessary delay in a reply.  It may be a good idea to spend another 10Rs and file a separate RTI for that question. In all probability, they will refer us back to the BBMP.

PS: FAQ for filing - railways link here.

 

 

 

suryakamal's picture

Re: STEEL GIRDERS FOR KADUGODI FLYOVER ?

up
194 users have liked.

Naveen,

Don't see any thing new on either side of the railway tracks?!

Neither there seems to be any news on the tender :(

 

What about celebrating 5th anniv of the railway bridge @ Kadugodi??

Regards...Surya 

Naveen's picture

Kadugodi - I saw it too

up
214 users have liked.

I noticed the same at Kadugodi whilst en-route to chennai & back by train. BTW, there are umpteen such bridges under construction in chennai & on the outskirts - noticed this during my visit there. Most of them have the framework ready till the tracks, but the spans (over the rail tracks) are missing & works are pending.

I guess the job requires some specialization as the unsupported spans are long - strength /safety might be the concern, but this should have been known to them even before venturing out to commence the job.

silkboard's picture

RTI - done

up
190 users have liked.

RTI is ready, will drop it in mailbox today.

silkboard's picture

5th Anniv of Rail Brodge - good idea!

up
208 users have liked.

5th anniv of Railway Bridge is a good idea. Can do this Gandhigiri style. May be hire a mobile music band and celebrate right at the railway crossing.

How many are game? Someone will have to take up the event planning responsibilities as I am tied up in Feb for couple of other Praja projects.

adityaselect's picture

Hard to believe

up
212 users have liked.

Guys,

I saw a dozen of people standing right at top of bridge. They were holding large piece of paper which liked a 'plan' & discussing....!

 

Somehow pressure needs to maintained....

 

-Thanks

sanjayv's picture

Contract details not posted yet (Jan 2010 data)

up
190 users have liked.

 The SWR railway lists the contracts awarded monthly.  The Kadugodi ROB is not listed in the latest list.  Maybe we'll know more by the same time next month.

 

See link here.

Naveen's picture

Kadugodi ROB - Ample space for support pillars

up
193 users have liked.

There is ample space between two tracks in the middle for erecting support pillars (there are a total of six tracks). In fact, the space is equivalent to the width of a platform at Whitefield station (see pictures below). Wonder why SWR has been working with the idea of an unsupported span of 42m length. Any thoughts on this ?

 

vandana kaul's picture

Let us all meet on the unconstructed Bridge and do a demo

up
204 users have liked.

Dear All,

        Luckily found this link and am happy to see that people are fighting and I wanted to do something about it as well.I stay in Golden Blossom and also go through this nightmare in and out.With in Blossoms we where thinking of go to all the apartments on this side and talking to the people about this idea that we have.Let us have a darna with kids .We need to have 100-150 kids and of course adults with them .We can have a demonstration on both the sides of the unconstructed brigde and we will in advance inform media ,police.We will go with a plan to make it grand to have maximum attention.If you guys this it is a good idea then we can work on it.

 

 

Regards

vandana

adityaselect's picture

why not try dharna

up
214 users have liked.

Hi Vandana, All,

Flyover matter has cooled off unlike few months back. Dharna seems to be the only option available with us.

Anyone has any ideas to co-ordinate and execute this ?

 

Thanks,

 Aditya

-Thanks

vandana kaul's picture

Let us have one and Gloden Blossom will try to intiate it

up
188 users have liked.

Dear All,

           We are open to doing this,we are not going to cause inconvenience to already suffering people,we will do it on the unconstructed ramps.We will make sure media is there and also take police permission.We need to meet and form an action plan for this we need help and support from other associations in the area.If people are ok with this idea,we are willing to take the lead to plan

 

 

Regards

 

murali772's picture

dharna route

up
197 users have liked.

@ Vandana - Do organise it. You can expect fair amount of support from the PRAJA community. But, to sustain it, the local community has to be in the lead.

All the best.

Muralidhar Rao
adityaselect's picture

More can join

up
208 users have liked.

Hi,

Please inform more of us at  surakshaahomes_blr@yahoogroups.com.

Thanks,

Aditya.

adityaselect@gmail.com

-Thanks

christopher's picture

Looks like work has restarted

up
194 users have liked.

Looks like the work has restarted on the bridge. Saw some welding work going on for the girders at the site next to the veterinary hospital close to the railway track. Another person who resides in our apartment also observed this and he even got the information that the work is awarded to some Balaji constructions.

I am not sure if this is the same, but their web site lists that one of their specialities is steel fabrication.  

sanjayv's picture

Any updates on the RTI?

up
207 users have liked.

SB,

  Any updates on the RTI? Did you get a tracking number for it to check status online? Just curious. 

suryakamal's picture

progress!!

up
208 users have liked.

Well, its bad news and good news!

Bad news: Coming from work @ 10:30 pm got stuck at the railway gate for about 20 mins. 

Good news: I could see, people working at the site (next to the police station)! At that time, had to resist the urge to get off the car and go and talk to them! Who knows, just as I step out, the gate could be opened and wake up the whole neighborhood with some 10 - 20 vehicles honking!

Looks like, this time, they are serious about finishing at last!!

Regards...Surya

sanjayv's picture

contract awarded?

up
171 users have liked.

According to Citizen matters comments, the contract has been awarded to a firm called KPR. Details awaited. 

adityaselect's picture

4months dealline

up
199 users have liked.

I have heard from builder that flyover would finish by June July ! Isnt it super :-)

Lot of work seems to be going on....hope it continues... lets keep our fingers crossed !

Cheers.....(finally)

Aditya

-Thanks

venkatem's picture

Latest Status

up
200 users have liked.

Aditya,

Thanks for sharing the good news.

Could you please update if the work is still progressing with the same pace. I live in US and heard from one of my real estate agent that the it has again stopped. He was also saying that they are discussing to demolish the flyover and start it all over again. Hopefully, this is just a rumour.

 

Thanks,

Venkatesh

pravn1984's picture

Jun 1st 2010 it must finish

up
187 users have liked.

@Venkatesh

As per this recent citizen matter article -> Citizen matters Info , the realistic deadline is June 1st 2010. Maybe someone on the ground can corroborate this info.

christopher's picture

"demolish the flyover and

up
200 users have liked.

"demolish the flyover and start it all over again" - this is not true. Infact the work on the bridge is going on at a very brisk pace. This time the June/July deadline seems realistic. They have erected some support pillars between the tracks which I believe are for the girders and will be removed after they are installed. In fact while I was driving by the bridge at around 3 am yesterday the work was going on and this is encouraging.

adityaselect's picture

Flyover completion will take much longer

up
201 users have liked.

Dear All,

From last few weeks there is no visible progress & it looks like the completion date of june/july will not be met.

We should again start over:

1)Mail to news papers

2)Exact completion date from RTI

3)A protest

 

Thanks !

 

-Thanks

sudeepb's picture

FLYOVER WORK IS IN PROGRESS

up
209 users have liked.

Hi !, Flyover work is in progress. They are laying cross bars on the girder. Thats takes time since the joints need top be strong and tested to bear the load of concrete and vehicles later on. 1st June is not possible but looks like should be over in another 2-3 months, provided funds keep flowing.. Lets keep our fingers crossed :-) Cheers ! ~ Sudeep

Praja.in comment guidelines

Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!



about seo | proj_announcement