BIAL Official Updates October 2007
Construction progress update for October 2007
The highlight this month included the commissioning of passenger boarding bridges, transformers, CCTV cameras, fire alarm system in the terminal building. Elevators were commissioned at both, the terminal building as well as the Air Traffic Control building. Airfield lights commissioning continued at the airside.
The Terminal building
The external painting of the west wall of the building continued. The works within the terminal building including the flooring, glass cladding of the columns, glass façade installations are nearing completion. The glass cladding for the 8 fixed links are in progress Installation work on other facilities like the elevators and escalators, automatic doors, check in counter, baggage handling system are continuing. The work within the duty free and food and beverage area on the first floor of the terminal building is gaining momentum.
Airside Works
The approach light work having been concluded at the runway, the work on the taxiway lights instillations is now nearing completion.
In addition, the instillation of light poles for the airside wall illumination is nearing completion. Cabling works for these are now in progress. On the Apron area, laying of the final concrete layer is nearing completion.
Other buildings & infrastructure
-At the ATC tower, the aluminium composite panel (ACP) cladding and glass fixing works are nearing completion.
-The earthworks for the main access road outside the boundary wall of the airport are nearing completion. Landscaping works along the main access road have now commenced.
-Nav-Aid (navigation aid) buildings: All the Nav-Aid buildings are nearly completed and are ready to be handed over to the Airports Authority of India.