Protest cum work review at the bridge work-site?

Okay, so we have had 3-4 comments expressing interest to participate in a protest sort of event near the work site. If 15-20 people can commit to attendance, let us fix a date and do it.

Transportation Infrastructure - wasted expenditure and mess

Where would underpasses, flyovers and then elevated flyovers leave us? 880 crores for 9.5 kms, almost a similar amount for Jalahalli elevated flyover, a third one for the BIAL to cost 680 crores as on date apart from several hundred crores spent in satiating similar needs in various wards of the city. What is the kind of infrastructural mess that is being created and touted as great w

New Year, new contract for Whitefield Railway bridge

Responses to the new tenders issued by the South Western Railways for completion of the Whitefield Railway overbridge project will be opened in the third week of this month, says a top official at the Railways.

Kadugodi ROB meet

16 Jan 2010 05:30
Asia/Calcutta

 Meet at Kadugodi rail over bridge location

Time: 11 AM

 

  • Take pics of work progress and post
  • Finalize the RTI application
  • Plan meeting local MLA or SWR officials

 

New completion date for Kadugodi flyover!?

See Page 18, Times of India - December 26,2009, SOUTH WESTERN RAILWAY (ROB-WFD-57R)

LINK FOR THE Same on the epaper:

http://epaper.timesofindi...

Workgroup for Kadugodi flyover (Whitefield)

Project number:2869
Opened by:mbhatia
Opened on:Tuesday, 15 December 2009 - 10:06pm
Last modified:Tuesday, 15 December 2009 - 10:06pm
Operations:add Project Task | view all project cases
Group to press for action and transparency on incomplete Kadugodi flyover

Project group to pool together efforts from various members to put pressure for action and transparency for completion of work on Kadugodi railway overbridge.

[Create by admin on behalf of mbhatia]

Bridge to Nowhere ! Hope now.

 Hi Guys,

I have sent a mail along with the attached photograph of Kadugodi flyover to our CM.

The same has been forwarded by him to BMP. I am hoping things may finally turn ourside now.

Cant forget to mention; It was a plesant surprise that our concern was acknowledged within three days.

 

Here is the picasa link - 

Plans for Belandur flyover?

This is my first post here. I live and work near the ORR in the Belandur Area. Have ben witnessing the chaos at the Belandur Jn on a daily basis(Although the traffic police do quite a good job to handle this intersection). I had read a lot on the plans for underpasses/flyovers a Belandur, Deevarabeesanahalli as part of the ORR signal free project.

ORR/OMR - Extra loop at K R Puram

Here is the plan BDA is going ahead with for this stretch. Anybody know what loop this is? Any idea what the improvement is? 

Rs 15 crore for the construction of additional loop and improvement of junction at K R Puram flyover

Praja.in comment guidelines

No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!